Costs expected for these categories for the coming year are as follows:
Maintenance |
$110376 |
Inspection |
$195640 |
The plant’s expected capacity is 74951 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job.
Direct materials |
$? |
Direct labour |
$6164 |
Machine hours |
390 |
Number of inspections |
8 |
Direct labour hours |
638 |
Total expected machine hours for all jobs during the year is 42719
and the total expected number of inspections is 2323.
Using activity-based costing and the appropriate cost drivers, if
the total cost of the proposed job is $10475 what is the direct
materials used in the job?
Select one:
a. $1706
b. $8794
c. $4311
d. $2630