Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
Inspection time | 0.2 | days |
Wait time (from order to start of production) | 15.4 | days |
Process time | 3.3 | days |
Move time | 1.3 | days |
Queue time | 4.1 | days |
Required:
1. Compute the throughput time. (Round your answer to 1 decimal place.)
2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.)
3. What percentage of the throughput time was spent in non–value-added activities? (Round your percentage answer to nearest whole percent.)
4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)
5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your percentage answer to 1 decimal place.)
Ans 1)
Throughput Time = Process Time + Inspection Time + Move Time + Queue Time
= 3.3 days + 0.2 days + 1.3 days + 4.1 days
= 8.9 days
Ans 2)
Manufacturing Cycle Efficiency = Value Added Time / Throughput Time
= 3.3 days / 8.9 days (Value Added time = Process Time)
= 37%
Ans 3)
Manufacturing Cycle Efficiency is 37% which means that out of total throughput time, time spent on value added activities was 37%. Therefore, time spent on non value added activities was 63% (100 - 37)
Ans 4)
Delivery Cycle Time = Wait Time + Throughput Time
= 15.4 days + 8.9 days
= 24.3 days
Ans 5)
New Throughput Time = Process Time + Inspection Time + Move Time
= 3.3 days + 0.2 days + 1.3 days
= 4.8 days
New Manufacturing Cycle Efficiency = Value added time / Throughput time
= 3.3 days / 4.8 days
= 68.8%