Question

Swimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists...

Swimming Pool Installation:

You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week.

ACTIVITY

Immediate Predecessor (s)

NORMAL TIME (NT)

CRASH TIME (CT)

Normal Cost (NC)

Crash Cost (CC)

A

--

2

1

7,000

10,000

B

--

2

2

3,000

3,000

C

A

3

1

12,000

40,000

D

B

3

2

12,000

28,000

E

C

1

1

8,000

8,000

F

D, E

5

3

5,000

15,000

G

E

3

2

9,000

18,000

A. Before crashing, the project duration is _________ week(s).

B. Swimming Pool Installation: The total cost of the project if we do nothing is $ __________ (round to the nearest dollar).

C. Swimming Pool Installation:  The minimum cost schedule is ________ week(s) (enter response as integer) .

D. Swimming Pool Installation:  The minimum cost schedule resulted in saving $________________ (enter response as integer).

Homework Answers

Answer #1

Since we needs to analyse the project cost and duration we draw the project network diagram as below;diagram drawn on the assemption that activity A & B are started from a basic step and the project is complting with Activity G

Normal Time and Crash Time Shown Seperatly

Answres

A. Before Crashing Project duration is 9 weeks( A+C+E+G)(2+3+1+3=9)

B. Total cost with normai time will be $171000 (A+C+E+G Plus Indirect cost of 15000 Per hour)(7000+12000+8000+9000+(15000*9)=171000)

C. 5 Weeks since using crash time the critical path will resoulting 5 weeks time(A+C+E+G) ( 1+1+1+2)

B. Minimum Schedule will save $ 46000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A...
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($) A — 4 1 5,000 8,000 B — 5 3 8,000 10,000 C A 1 1 4,000 4,000 D B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F D 7 6 4,000 7,000 You are the manager of a project to improve a billing process at your firm. Table 3 contains the data you will need to conduct a cost analysis...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed...
All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities: Immediate Time (weeks) Cost ($1000s) Activity Description Predecessor(s) Normal Crash Normal Crash A Plan needs...
A car dealership decided to add an annex to its sales office as a customer lounge....
A car dealership decided to add an annex to its sales office as a customer lounge. The project is divided into the activities listed in the following table. The immediate predecessor(s), times and costs, both normal and crashed, are given. To finish the project sooner, the dealership has to make time and cost tradeoffs. If the project needs to be finished in 25 weeks, you are required to formulate a linear programming model to decide about how much to crash...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss...
Mega Mart Store is a discount department store badly in need of renovation. To avoid loss of sales and disruption of customer shopping habits, Mega Mart wants to complete this renovation without closing the store itself, by temporarily co-locating goods from one area of the store into another, creating open spaces for renovation and re-occupation. Mega Mart is divided into four basic areas of goods: Clothing, Electronics, House Wares and Foodstuffs. Each of these areas will need to be temporarily...
can you please answer question 14-17. thank you, please show your work. Using the following information...
can you please answer question 14-17. thank you, please show your work. Using the following information find the ratios listed: Hamilton Company Comparative Balance Sheets December 31, 2018 and December 31, 2019 Assets         2018      2019   Difference Cash              15,000              47,000         32,000 Accounts Receivable              55,000              47,000         (8,000) Inventory           110,000           144,000         34,000 Prepaid Expenses                5,000                1,000         (4,000) Long term investments           127,000           115,000       (12,000) Land             55,000             55,000...
Can you please answer question 5-8. Thank you please show your work. Using the following information...
Can you please answer question 5-8. Thank you please show your work. Using the following information find the ratios listed: Hamilton Company Comparative Balance Sheets December 31, 2018 and December 31, 2019 Assets         2018      2019   Difference Cash              15,000              47,000         32,000 Accounts Receivable              55,000              47,000         (8,000) Inventory           110,000           144,000         34,000 Prepaid Expenses                5,000                1,000         (4,000) Long term investments           127,000           115,000       (12,000) Land             55,000             55,000...
Using the following information find the ratios listed: Hamilton Company Comparative Balance Sheets December 31, 2014...
Using the following information find the ratios listed: Hamilton Company Comparative Balance Sheets December 31, 2014 and December 31, 2015 Assets         2014      2015   Difference Cash              15,000              47,000         32,000 Accounts Receivable              55,000              47,000         (8,000) Inventory           110,000           144,000         34,000 Prepaid Expenses                5,000                1,000         (4,000) Long term investments           127,000           115,000       (12,000) Land             55,000             55,000                   -   Building           450,000           660,000       210,000 Accumulated Depr -...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT