Question

Davis Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year,...

Davis Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the total estimated manufacturing overhead was $224,580 and the estimate of direct labor hours was 6,000. Job #145 was completed with 4 direct labor hours. How much overhead was applied to Job #145?

a.) 0.11

b.) 149.72

c.) 37.43

d.) 0

Homework Answers

Answer #1

Answer: $149.72

Explanation:

Given that company uses direct labour hours as the basis for allocation of overhead.

Estimated Manufacturing Overhead= $224,580

Estimated direct labour hours= 6,000 hours

Therefore, Predetermined Overhead rate= Total estimated manufacturing overhead/ Total estimated labour hours

= 224,580 / 6,000

= $37.43 per direct labour hour

Number of Direct Labour hours used in Job #145= 4 hours

Therefore, Overhead applied to Job #145 = $37.43 * 4 hours

= $149.72

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Daguio corporation uses direct labor hours in its predetermined overhead rate. At the beginning of the...
Daguio corporation uses direct labor hours in its predetermined overhead rate. At the beginning of the year the total estimated manufacturing overhead was $224,580. At the end of the year actual direct labor hours for the year were 18,200 hours manufacturing overhead for the year was under applied by 12,100, and the actual manufacturing overhead was $219,580. The predetermined overhead rate for the year must have been closest to
Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year,...
Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the estimated direct labor-hours were 22,100 hours and the total estimated manufacturing overhead was $570,180. At the end of the year, actual direct labor-hours for the year were 22,050 hours and the actual manufacturing overhead for the year was $570,180. Overhead at the end of the year was:
Dagger Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year,...
Dagger Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the total estimated manufacturing overhead was $240,850. At the end of the year, actual direct labor-hours for the year were 15,300 hours, manufacturing overhead for the year was underapplied by $15,000, and the actual manufacturing overhead was $236,850. The predetermined overhead rate for the year must have been closest to: $14.50 $15.44 $13.63 $15.16
Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year,...
Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the estimated direct labor-hours were 22,120 hours and the total estimated manufacturing overhead was $575,120. At the end of the year, actual direct labor-hours for the year were 22,100 hours and the actual manufacturing overhead for the year was $575,120. Overhead at the end of the year was: (Round your intermediate calculations to 2 decimal places.)
Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year,...
Crich Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the estimated direct labor-hours were 21,800 hours and the total estimated manufacturing overhead was $497,040. At the end of the year, actual direct labor-hours for the year were 21,500 hours and the actual manufacturing overhead for the year was $492,040. Overhead at the end of the year was: $1,840 underapplied $6,840 overapplied $6,840 underapplied $1,840 overapplied
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $678,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 30 Total direct labor-hours 300 Direct materials $ 1,350 Direct labor cost $ 11,400...
2. Sigma Corporation estimates its plantwide predetermined overhead rate annually on the basis of direct labor-hours....
2. Sigma Corporation estimates its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 34,000 direct labor-hours would be required for the period’s estimated level of production. The company also estimated $559,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $4.00 per direct labor-hour. Sigma’s actual manufacturing overhead cost for the year was $758,696 and its actual total direct labor was 34,500 hours....
Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 58,000 direct labor-hours, total fixed manufacturing overhead cost of $58,000, and a variable manufacturing overhead rate of $2.90 per direct labor-hour. Recently Job X387 was completed and required 220 direct labor-hours. Required: Calculate the amount of overhead applied to Job X387
Sawyer Manufacturing Corporation uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead...
Sawyer Manufacturing Corporation uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Last year, the Corporation worked 41,000 actual direct labor-hours and incurred $624,000 of actual manufacturing overhead cost. The Corporation had estimated that it would work 39,000 direct labor-hours during the year and incur $585,000 of manufacturing overhead cost. The Corporation's manufacturing overhead cost for the year was:
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT