The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $1,678. A total of 30 direct labor-hours and 46 machine-hours were worked on the job. The direct labor wage rate is $12 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $18 per machine-hour. What is the total cost for Job 450?
a.) 2,770
b.) 2,590
c.) 1,754
d.) 2,866
Direct materials = $1,678
Direct labor hours = 30
Machine hours = 46
Direct labor rate = $12 per labor hour
Direct labor cost = Direct labor hours x Direct labor rate
= 30 x 12
= $360
Predetermined overhead rate = $18 per machine hour
Manufacturing overhead applied = Machine hours x Predetermined overhead rate
= 46 x 18
= $828
Total cost = Direct materials + Direct labor cost + Manufacturing overhead applied
= 1,678+360+828
= $2,866
The total cost for Job 450 = $2,866
Correct option is d.