Question

An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a...

An inventory item of XYZ Manufacturing has an average daily demand of 10 units with a maximum daily demand of 12 units. The economic order quantity is 200 units. Without safety stocks, the reorder point is 50 units. Safety stocks are set at 94 units.

Required:
a. Determine the reorder point with safety stocks.
b. Determine the maximum inventory level.
c. Determine the average lead time. d. Determine the maximum lead time

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
MNO has an average annual demand for red, medium polo shirts of 100,000 units. The cost...
MNO has an average annual demand for red, medium polo shirts of 100,000 units. The cost of placing an order is $500 and the cost of carrying one unit in inventory for one year is $20. Required: a. Use the economic-order-quantity model to determine the optimal order size. b. Determine the reorder point assuming a lead time of 12 days and the store is open 250 days in the year. c. Determine the safety stock required to prevent stockouts assuming...
Q. Daily demand for a product is normally distributed with a mean M= 12 units and...
Q. Daily demand for a product is normally distributed with a mean M= 12 units and standard deviation Q= 4 units. Lead time is 9 days. The order quantity for this item is set at a 12-day supply. a. If a minimum probability of satisfying demand per cycle of 0.80 is desired, what is the reorder point? b. If a fill rate of 9% is desired, what is the reorder point?
16) For supply item ABC, Andrews Company has been ordering 125 units based on the recommendation...
16) For supply item ABC, Andrews Company has been ordering 125 units based on the recommendation of the salesperson who calls on the company monthly. A new purchasing agent has been hired by the company who wants to start using the economic-order-quantity method and its supporting decision elements. She has gathered the following information: Annual demand in units 250 Days used per year 250 Lead time, in days 10 Ordering costs $100 Annual unit carrying costs $20 Required: Determine the...
The reorder point r = dm is defined as the lead-time demand for an item. In...
The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with...
Bob Sean, manager at Ikea is responsible for managing the inventory of computer desks. Bob isn't...
Bob Sean, manager at Ikea is responsible for managing the inventory of computer desks. Bob isn't talkative about his inventory, but you have managed to extract the following information from him: It costs $35 to place an order. Each computer desk costs $31.33. Annual per unit holding cost is 30% of item value. Average daily demand is 100 writing desks. Standard deviation of demand during lead time is 51.96. Lead time to receive a computer desk from a supplier is...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20...
Daily demand for neckties at a MegaMart store is normally distributed with a mean of 20 units and a standard deviation of 7. The supplier, Suits Galore, takes on average about 9 days to supply a MegaMart order. The standard deviation of lead time is 3 days. MegaMart is targeting a customer service level of 95 percent (z = 1.65) and monitors its inventory continuously. How much safety inventory of neckties should MegaMart carry? What should their reorder point (ROP)...
Lead Time Demand for an item we keep in stock is 420 units, with a standard...
Lead Time Demand for an item we keep in stock is 420 units, with a standard deviation of 44 units. What service level is achieved with our current Reorder point of 442 units? What Reorder Point should be used in order to accomplish a service level of 97%?
Problem 14-3 (Algorithmic) The reorder point r = dm is defined as the lead-time demand for...
Problem 14-3 (Algorithmic) The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order...
Clothing Company manufactures uniforms. A heavy duty fabric is one part that the company orders from...
Clothing Company manufactures uniforms. A heavy duty fabric is one part that the company orders from an outside supplier. Information pertaining to the strap is as follows: Economic Order Quantity 4,300 units Average Daily Usage 420 Maximum Daily Usage 490 Lead Time 9 days PART A What is the reorder point assuming no safety stock is carried? PART B What is the reorder point assuming that safety stock is carried?
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units...
For a particular SKU, the lead time is 6 weeks, the average demand is 100 units a week, and safety stock is 200 units. What is the average inventory if 10 weeks’ supply is ordered at one time? What is the order point? The standard deviation of demand during the lead time is 100 units. Calculate the safety stock required for the following service levels: 75%, 80%, 85%, 90%, 95%, and 99.99%. Calculate the change in safety stock required to...