Tonopah Corporation (TC) wants to move from a job costing system to an activity based costing...

Tonopah Corporation (TC) wants to move from a job costing system to an activity based costing (ABC) system. For 2019, Tonopah Corporation has budgeted sales of 25,000 units for product beta and 125,000 units for product gamma. TC estimates total manufacturing overhead to be $6,000,000. TC’s traditionally applied manufacturing overhead to products based on direct labor hours. Product beta and product gamma both require 2.75 hours of direct labor to complete. Unit costs for materials and labor are as follows:

Direct materials product beta = $75; product gamma = $25. Direct labor product beta = $20; product gamma = $20.

1) What is the POHR based on labor hours?

2) Using direct labor hours as a base, what is the unit product costs? (8 pts)

Beta Gamma

Direct Materials

Direct Labor

Manuf Overhead

Unit Product Costs

Homework Answers

Answer #1

The answer has been presented in the supporting sheet. For detailed answer refer to the supporting sheet.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 26,000 direct labor-hours, total fixed manufacturing overhead cost of $195,000, and a variable manufacturing overhead rate of $2.10 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 400...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 38,000 direct labor-hours, total fixed manufacturing overhead cost of $250,800, and a variable manufacturing overhead rate of $2.40 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 400...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 42,000 direct labor-hours, total fixed manufacturing overhead cost of $361,200, and a variable manufacturing overhead rate of $2.40 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 200...
Cull Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Cull Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $370,500, variable manufacturing overhead of $3.00 per machine-hour, and 57,000 machine-hours. The company has provided the following data concerning Job X455 which was recently completed: Number of units in the job 10 Total machine-hours 80 Direct materials $ 750 Direct labor cost $ 1,500 If...
Cull Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Cull Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $546,700, variable manufacturing overhead of $2.00 per machine-hour, and 77,000 machine-hours. The company has provided the following data concerning Job X455 which was recently completed: Number of units in the job 20 Total machine-hours 80 Direct materials $ 840 Direct labor cost $ 1,680 If...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 47,000 Total fixed manufacturing overhead cost $ 202,100 Variable manufacturing overhead per direct labor-hour $ 2.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials $ 850 Direct labor cost $...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $678,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 30 Total direct labor-hours 300 Direct materials $ 1,350 Direct labor cost $ 11,400...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 94,000 Total fixed manufacturing overhead cost $ 404,200 Variable manufacturing overhead per direct labor-hour $ 4.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials $ 660 Direct labor cost $...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $ 96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 755 Direct labor cost $...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,500 Total fixed manufacturing overhead cost $455,000 Variable manufacturing overhead per machine-hour $ 5.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 710 Direct labor cost $1,420 If the company marks...