Question

Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system.

A typical departmental cost report for a recent period follows:


Assembly Department
Cost Report
For the Month Ended March 31
Actual Results Planning Budget Variances
  Machine-hours 25,000   30,000  
  Variable costs:
     Supplies $ 6,600    $ 7,200 $ 600   F
     Scrap 19,600    21,000 1,400   F
     Indirect materials 61,400    70,500 9,100 F
  Fixed costs:    
     Wages and salaries 66,700    64,000 2,700   U
     Equipment depreciation 94,000    94,000 –  
  Total cost $ 248,300    $ 256,700   $ 8,400 F

  

    After receiving a copy of this cost report, the supervisor of the Assembly Department stated, “These reports are super. It makes me feel really good to see how well things are going in my department. I can’t understand why those people upstairs complain so much about the reports.”

    For the last several years, the company’s marketing department has chronically failed to meet the sales goals expressed in the company’s monthly budgets.


Required:
1.

The company’s president is uneasy about the cost reports, what can be the reason? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)

     

Cost reports are ineffective since budgeted costs at one level of activity are compared to actual costs at another level of activity.
Cost reports show whether fixed costs are controlled and do not show whether variable costs are controlled.
Cost reports are effective since budgeted costs at one level of activity are compared to actual costs at another level of activity.
Cost reports show whether fixed costs and variable costs are controlled.


2.

What kind of reports should be used to give better insight into how well departmental supervisors are controlling costs?

Flexible budget performance reports must be used
Fixed budget performance reports must be used


3.

Complete the new performance report for the quarter, based on Flexible Budget Performance approach. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)

      

4. Were costs well controlled in March?
Costs were well controlled
Costs were not well controlled


Homework Answers

Answer #1
1
Cost reports are ineffective since budgeted costs at one level of activity are compared to actual costs at another level of activity.
Cost reports show whether fixed costs and variable costs are controlled.
2
Flexible budget performance reports must be used
3
Actual results Spending variances Flexible budget Activity variances Planning budget
Machine hours 25000 25000 30000
Supplies 6600 600 U 6000 1200 F 7200
Scrap 19600 2100 U 17500 3500 F 21000
Indirect materials 61400 2650 U 58750 11750 F 70500
Wages and salaries 66700 2700 U 64000 0 None 64000
Equipment depreciation 94000 0 None 94000 0 None 94000
Total 248300 8050 U 240250 16450 F 256700
4
Costs were not well controlled
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 25,000 30,000 Variable costs: Supplies $ 6,600 $ 7,200 $ 600 F...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 15,000 20,000 Variable costs: Supplies $ 8,700 $ 9,300 $ 600 F...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 25,000 30,000 Variable costs: Supplies $ 7,500 $ 8,100 $ 600 F...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 25,000 30,000 Variable costs: Supplies $ 7,200 $ 7,800 $ 600 F...
Problem 9-25 Critiquing a Variance Report; Preparing a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] Several...
Problem 9-25 Critiquing a Variance Report; Preparing a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning...
True Or False 1- Fixed costs should not be included in a flexible budget because they...
True Or False 1- Fixed costs should not be included in a flexible budget because they do not change when the level of activity changes. (       ) 2-To help assess how well a manager has controlled costs, actual costs should be compared to what the costs should have been for the actual level of activity. (       ) 3-The activity variance for revenue is favorable if the actual revenue for the period exceeds the revenue in the static planning budget. (      ...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget formula for the activity. The following resources are used by the activity: Four welding units, with a lease cost of $14,000 per year per unit Six welding employees each paid a salary of $55,000 per year (A total of 12,000 welding hours are supplied by the six workers.) Welding supplies: $400 per job Welding hours: 4 hours used per job During the year, the...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget formula for the activity. The following resources are used by the activity: • Four welding units, with a lease cost of $12,000 per year per unit • Six welding employees each paid a salary of $52,000 per year (A total of 9,000 welding hours are supplied by the six workers.) • Welding supplies: $300 per job • Welding hours: 3 hours used per job...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget formula for the activity. The following resources are used by the activity: Four welding units, with a lease cost of $14,000 per year per unit Six welding employees each paid a salary of $45,000 per year (A total of 12,000 welding hours are supplied by the six workers.) Welding supplies: $400 per job Welding hours: 4 hours used per job During the year, the...
Problem 22-1A Responsibility accounting performance reports; controllable and budgeted costs LO P1 Billie Whitehorse, the plant...
Problem 22-1A Responsibility accounting performance reports; controllable and budgeted costs LO P1 Billie Whitehorse, the plant manager of Travel Free’s Indiana plant, is responsible for all of that plant’s costs other than her own salary. The plant has two operating departments and one service department. The camper and trailer operating departments manufacture different products and have their own managers. The office department, which Whitehorse also manages, provides services equally to the two operating departments. A budget is prepared for each...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • Derive the trigonometric Fourier series of the following periodic square wave and reduce as far as...
    asked 5 minutes ago
  • [1] A certain forest has three creatures: rabbits, squirrels, and foxes. The rabbits eat green stuff,...
    asked 16 minutes ago
  • What does it mean to monetize the deficit and why is it especially inflationary? Thanks! (Macroeconomics)
    asked 32 minutes ago
  • Unit 3 Dropbox Assignment Page CHAPTER 5 ANSWER CHOICES—CARDIOVASCULAR AND LYMPHATIC SYSTEMS  angina pectoris ...
    asked 43 minutes ago
  • Consider the autonomous first-order differential equation dy/dx=4y-(y^3). 1. Classify each critical point as asymptotically stable, unstable,...
    asked 55 minutes ago
  • Any athlete who fails the Enormous State University's women's soccer fitness test is automatically dropped from...
    asked 56 minutes ago
  • A friend at work has lunch with you every day, Monday through Friday. This female friend...
    asked 59 minutes ago
  • Consider the probability distribution of the discrete random vector [X,Y] where X represents the number of...
    asked 1 hour ago
  • a diver springs upward from a board that is 2.92 meters above water . At the...
    asked 1 hour ago
  • Determine the volumes of each solution you would use to prepare a 1.0L of a pH...
    asked 2 hours ago
  • For grade-level structures such as building slabs and highway pavements (no deep foundations), other approaches to...
    asked 2 hours ago
  • If I have 500 acres of land, how do I convert to the unit measurement of...
    asked 2 hours ago