Question

A is considering the investment in a project that has an initial cash outlay followed by...

A is considering the investment in a project that has an initial cash outlay followed by a series of net cash inflows. The business applied the NPV and IRR methods to evaluate the proposal but, after the evaluation had been undertaken, it was found that the correct cost of capital figure was lower than that used in the evaluation. What will be the effect of correcting for this error on the NPV and IRR figures? Effect on NPV IRR

a) Decrease Decrease

b) Decrease No change

c) Increase Increase

d) Increase No Change

e) Increase Decrease

Homework Answers

Answer #1
Using a wrong cost of capital figure would only affect NPV (Net Present value)
Net Present value is calculated using cost of Capital. The cash flows are discounted at cost of capital.
The lower the cost of capital, the higher the PV factor and NPV.
Correcting the error and using correct cost of capital figure would lead to higher PV factor and increased NPV.
The internal rate of return (IRR) would be unaffected by Cost of Capital.
Option D Increase No Change is correct
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
If you assume that a project being considered has normal cash flows, with one outflow followed...
If you assume that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which statement would be correct? Question 11 options: a) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. b) If a project's NPV is less than zero, then its IRR must be less than the cost of capital. c) A project’s NPV is found by compounding the cash inflows...
If a project being considered has normal cash flows, with one outflow followed by a series...
If a project being considered has normal cash flows, with one outflow followed by a series of inflows, which of the following statements is CORRECT? A If a project's NPV is greater than zero, then its IRR must be less than the WACC. B If a project's NPV is greater than zero, then its IRR must be less than zero. C The higher the WACC used to calculate the NPV, the lower the calculated NPV will be. D A project's...
ABC company is considering a project that calls for an initial cash outlay of $50,000. The...
ABC company is considering a project that calls for an initial cash outlay of $50,000. The expected net cash inflows from the project are $7,791 for each of 10 years. What is the IRR of the project?
ABC company is considering a project that calls for an initial cash outlay of $50,000. The...
ABC company is considering a project that calls for an initial cash outlay of $50,000. The expected net cash inflows from the project are $7,791 for each of 10 years. What is the IRR of the project?
Alcan, Inc. is considering a project that has an initial outlay or cost of $220,000. The...
Alcan, Inc. is considering a project that has an initial outlay or cost of $220,000. The respective future cash inflows from its four-year project for years 1 through 4 are: $50,000, $60,000, $70,000, and $80,000, respectively. Alcan uses the internal rate of return method to evaluate projects. Will Alcan accept the project if its hurdle rate is 12%? Alcan will not accept this project because its IRR is about 7.63%. Alcan will not accept this project because its IRR is...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. A: The NPV of a relatively low-risk project should be found using a relatively high WACC B: The lower the WACC used to calculate it, the lower the calculated NPV will be If a project’s NPV is greater than zero, then its IRR must be less than zero C: If a project’s NPV is...
Flynn, Inc. is considering a four-year project that has an initial after-tax outlay or after-tax cost...
Flynn, Inc. is considering a four-year project that has an initial after-tax outlay or after-tax cost of $80,000. The future after-tax cash inflows from its project for years one, two, three, and four are $40,000, $40,000, $30,000, and $30,000, respectively. Flynn uses the internal rate of return method to evaluate projects. What is the approximate IRR for this project? The IRR is less than 12%. The IRR is between 12% and 20%. The IRR is about 24.55%. The IRR is...
Which of the following statements is correct? Assume the project being considered has normal cash flows,...
Which of the following statements is correct? Assume the project being considered has normal cash flows, with one outflow, followed by a series of inflows: If a project’s NPV is > 0, the IRR must be less than WACC The higher the WACC used to calculate NPV, the lower the calculated NPV will be The NPV’s of relatively risky projects should be found using relatively low WACC’s If a project’s NPV is > 0, the IRR must be less than...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. If a project's NPV is less than zero, then its IRR must be less than the cost of capital. If a project's NPV is greater than zero, then its IRR must...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The NPVs of relatively risky projects should be found using relatively low costs of capital. b. If a project's NPV is greater than zero, then its IRR must be less than the cost of capital. c. The higher the cost of capital used to calculate the NPV, the lower the calculated NPV will...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT