Question

On January 2, 2020, Oriole Company began construction of a new citrus processing plant. The automated...

On January 2, 2020, Oriole Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows:

Oriole Company borrowed $3300000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company also had $13560000 in 7% bonds outstanding in 2020 and 2021.

The interest capitalized for 2020 was:

  1. $482340

  2. $158200

  3. $474600

  4. $120660

Answer:

January 2, 2020 $ 603000

September 1, 2020 1810800

December 31, 2020 1810800

March 31, 2021 1810800

September 30, 2021 1218000

Homework Answers

Answer #1
Answer:
Option D is correct. i.e $120660
Interest Capitalized for 2020
Date Expenditure Weight Average
02-Jan-20 603000 12/12 603000
01-Sep-20 1810800 4/12 603600
31-Dec-20 1810800 0/12                              -  
Accumulated   Expenditures 4224600 1206600
Interest Capitalized for 2020 = 1206600 x 10% = 120660
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 2, 2012, Dessin Ltd began construction of a new citrus processing plant. The automated...
On January 2, 2012, Dessin Ltd began construction of a new citrus processing plant. The automated plant was finished and ready for use on December 31, 2012. Expenditures for the construction were as follows: January 2, 2012 $150,000 March 1, 2012 700,000 September 1, 2012 500,000 December 1, 2012 180,000 December 31, 2012 200,000 Dessin Ltd borrowed $500,000 on a construction loan at 10% interest on January 2, 2012. This loan was outstanding during the construction period. The company also...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 72 October 1, 2020 40 February 1, 2021 48 April 1, 2021 30 September 1, 2021 29 October 1, 2021 15 On July 1, 2020, Crocus obtained a $88 million construction loan with a 10% interest rate. The loan was outstanding through the end of...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,050,000 at 11% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $6,000,000, 16% bonds $4,000,000, 11% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 840,000 March 31 1,440,000 June 30 1,088,000 September 30 840,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 330,000 September 1, 2018 $ 495,000 December 31, 2018 $ 495,000 March 31, 2019 $ 495,000 September 30, 2019 $ 330,000 Dreamworld had $6,500,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 328,000 September 1, 2018 $ 486,000 December 31, 2018 $ 486,000 March 31, 2019 $ 486,000 September 30, 2019 $ 328,000 Dreamworld had $6,200,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 343,000 September 1, 2018 $ 501,000 December 31, 2018 $ 501,000 March 31, 2019 $ 501,000 September 30, 2019 $ 343,000 Dreamworld had $6,700,000 in 14% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?