The following data relate to labor cost for production of 5,200 cellular telephones: Actual: 3,500 hrs. at $15.60 Standard: 3,440 hrs. at $15.90 a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Rate variance $ Time variance $ Total direct labor cost variance $ b. The employees may have been less-experienced or poorly trained, thereby resulting in a labor rate than planned. The lower level of experience or training may have resulted in efficient performance. Thus, the actual time required was than standard.
Ans. A | Labor rate variance = (Actual rate - Standard rate) * Actual hours | ||
($15.60 - $15.90) * 3,500 | |||
-$0.30 * 3,500 | |||
-$1,050 | Favorable | ||
Labor time variance = (Actual hours - Standard hours) * Standard rate | |||
(3,500 - 3,440) * $15.90 | |||
60 * $15.90 | |||
$954 | Unfavorable | ||
Total direct labor cost variance = Labor time variance + Labor rate variance | |||
$954 + (-$1,050) | |||
$954 - $1,050 | |||
-$96 | Favorable | ||
Ans. B | The employees may have been less-experienced or poorly trained, thereby resulting in a | ||
lower labor rate than planned. The lower level of experience or training may have resulted | |||
in less efficient performance. Thus, the actual time required was more than standard. |