Question

WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data: Direct Materials  ...

WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data:

Direct Materials   12 pounds             @            $ 2.00 per pound

Direct Labor         2 DLH                 @            $15.00 per DLH

Variable MOH     1 MHR                @            $10.00 per MHR

Fixed MOH          1 MHR                @            $20.00 per MHR

Production was forecast to be 2,000 units, but only 1,950 were actually produced. 26,000 pounds of materials were purchased for $66,300. A total of 23,000 pounds of materials were used in production. Actual direct labor totaled 4,000 DLH, costing $48,000. Forecast variable overhead was $10,000, and forecast fixed overhead was $40,000. Actual variable overhead was $11,000. Actual fixed overhead was $38,000. Actual machine hours totaled 1,900 MHR.

16THE ANSWER IS e11.          (5 POINTS) Calculate the direct materials price variance.       ANSWER: __________________

               

17THE ANSWER IS e11.          (5 POINTS) Calculate the direct materials usage variance.      ANSWER: ___________________

18THE ANSWER IS e11.          (5 POINTS) Calculate the direct labor efficiency variance.      ANSWER: ___________________

19THE ANSWER IS e11.          (5 POINTS) Calculate the direct labor rate variance.                 ANSWER: _________________

20THE ANSWER IS e11.          (5 POINTS) Calculate the variable overhead efficiency variance.

                                                                                                                                ANSWER: ___________________

21THE ANSWER IS e11.          (5 POINTS) Calculate the variable overhead spending (or budget) variance.

                                                                                                                                ANSWER: ___________________

Homework Answers

Answer #1
Calculate the direct materials price variance
(Std.price-actual price)*actual units produced
(2-66300/26000)*26000
-14300 (A)
Calculate the direct materials usage variance
(Std.usage-actual usage)*Std.price
(12*2000-23000)*2
2000 (F)
Calculate the direct labor rate variance
(Std.price-actual price)*actual hours
(15-48000/4000)*4000
12000 (F)
Calculate the variable overhead efficiency variance.
(actual hours-Std.hrs)*Std.overhead rate
(1900-1950)*10
-500 (F)
Calculate the variable overhead spending
(10*1950)
19500
Calculate the direct labor efficiency variance
(actual hours-Std.hrs)*Std.labor rate
(4000-2*1950)*15
1500 (A)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data: Direct Materials...
WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data: Direct Materials 12 pounds @ $ 2.00 per pound Direct Labor   2 DLH @ $15.00 per DLH Variable MOH   1 MHR @ $10.00 per MHR Fixed MOH   1 MHR @ $20.00 per MHR Production was forecast to be 2,000 units, but only 1,950 were actually produced. 26,000 pounds of materials were purchased for $66,300. A total of 23,000 pounds of materials were used in production. Actual...
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor....
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead​ (both variable and​ fixed) is allocated to products on the basis of standard direct manufacturing labor hours​ (DLH). At the beginning of 2014 Brown adopted the following standards for its manufacturing​ costs:  Direct materials 3 lbs. at $4 per lb. $12.00 Direct manufacturing labor 4 hrs. at $20 per hr. 80.00 Manufacturing overhead: Variable $6 per DLH 24.00 Fixed $7 per DLH...
Mike Manufacturing has the following standard cost sheet for one of its products: Direct materials (6...
Mike Manufacturing has the following standard cost sheet for one of its products: Direct materials (6 ft. @ $5) $30 Direct labour (1.5 hours @$10) 15 Variable overhead (1.5 hours@ $4) 6 Fixed overhead (1.5 hours@ $2*) 3 Standard unit cost 54 The rate based on expected activity of 17,000 hours. During the most recent year, the following actual results were recorded: Production 12,000 units Fixed overhead $33,000 Variable overhead $69,000 Direct materials (71,750 ft. purchased) $361,620 Direct labour (17,900...
SUPERIOR PRODUCED 1000 UNITS OF FINISH PRODUCTS IN 2018: Direct materials cost variance $115 U Direct...
SUPERIOR PRODUCED 1000 UNITS OF FINISH PRODUCTS IN 2018: Direct materials cost variance $115 U Direct materials efficiency variance 840 F Direct labor cost variance 700 F Direct labor efficiency variance 6,450 F Variable overhead cost variance 1,000 U Variable overhead efficiency variance 1,000 F Fixed overhead cost variance 700 U Fixed overhead volume variance Standards: 3 yards of cloth per unit at $1.20 per yard 2 direct labor hours per unit at $10.75 per hour Overhead allocated at $5.00...
Standards (for a planned level of production of 2,200 units per month) Direct Materials: Yards per...
Standards (for a planned level of production of 2,200 units per month) Direct Materials: Yards per costume12.50yards,, Price per yard $26.00average Direct Labor: D.L. Hours per costume 62.00hours,, D.L. Rate per hour $44.50average Variable MOH standard rate per direct labor hour $4.35per D.L. hour,,Fixed MOH standard rate per direct labor hour $9.47per D.L. hour,,Total Budgeted Fixed MOH (for 1 month) $ 1,250,000 Actual cost and data from the current month: Actual number of yards of materials purchased 28,500 Actual cost...
6-25 Comprehensive variance calculations (LO 2, 4, 6, 7) Carson Construction Consultants performs cement core tests...
6-25 Comprehensive variance calculations (LO 2, 4, 6, 7) Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company's controller, Landon Carson, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound    4 pounds $ 2.00 Direct labor $10 per DLH   .5 DLH   5.00 Variable overhead $9 per DLH   .5 DLH   4.50 Fixed overhead $16 per DLH   ...
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor....
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead​ (both variable and​ fixed) is allocated to products on the basis of standard direct manufacturing labor hours​ (DLH). At the beginning of 2014 Brown adopted the following standards for its manufacturing​ costs:  Direct materials 3 lbs. at $4 per lb. $12.00 Direct manufacturing labor 4 hrs. at $20 per hr. 80.00 Manufacturing overhead: Variable $6 per DLH 24.00 Fixed $7 per DLH...
Zee Corporation has developed the following cost standards for the production of its leather backpacks: Standard...
Zee Corporation has developed the following cost standards for the production of its leather backpacks: Standard Cost Per Backpack Leather (2.0 yards × $25 per yard) $50.00 Direct labor (2.3 hours × $10.00 per hour) $23.00 Variable overhead (2.3 hours × $16.00 per hour) $36.80 Variable overhead at Zee is applied on the basis of direct labor hours. The actual results for last month were as follows: Number of backpacks produced 12,500 Direct labor hours incurred 27,950 Yards of leather...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget...
Beakins Company produces a single product. The standard cost card for the product follows: Direct materials...
Beakins Company produces a single product. The standard cost card for the product follows: Direct materials (4 yards @ $5 per yard)............................. $20 Direct labor (1.5 hours @ $10 per hour).............................. $15 Variable manufacturing overhead (1.5 hrs. @ $4 per hour) $6 During a recent period the company produced 1,200 units of product. Various costs associated with the production of these units are given below: Direct materials purchased (6,000 yards)..... $29,400 Direct materials used in production................ 5,120 yards Direct labor...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT