WizzleCo produces bicycles. The following standard cost sheet has been developed from historical data:
Direct Materials 12 pounds @ $ 2.00 per pound
Direct Labor 2 DLH @ $15.00 per DLH
Variable MOH 1 MHR @ $10.00 per MHR
Fixed MOH 1 MHR @ $20.00 per MHR
Production was forecast to be 2,000 units, but only 1,950 were actually produced. 26,000 pounds of materials were purchased for $66,300. A total of 23,000 pounds of materials were used in production. Actual direct labor totaled 4,000 DLH, costing $48,000. Forecast variable overhead was $10,000, and forecast fixed overhead was $40,000. Actual variable overhead was $11,000. Actual fixed overhead was $38,000. Actual machine hours totaled 1,900 MHR.
16THE ANSWER IS e11. (5 POINTS) Calculate the direct materials price variance. ANSWER: __________________
17THE ANSWER IS e11. (5 POINTS) Calculate the direct materials usage variance. ANSWER: ___________________
18THE ANSWER IS e11. (5 POINTS) Calculate the direct labor efficiency variance. ANSWER: ___________________
19THE ANSWER IS e11. (5 POINTS) Calculate the direct labor rate variance. ANSWER: _________________
20THE ANSWER IS e11. (5 POINTS) Calculate the variable overhead efficiency variance.
ANSWER: ___________________
21THE ANSWER IS e11. (5 POINTS) Calculate the variable overhead spending (or budget) variance.
ANSWER: ___________________
Calculate the direct materials price variance | |||||
(Std.price-actual price)*actual units produced | |||||
(2-66300/26000)*26000 | |||||
-14300 | (A) | ||||
Calculate the direct materials usage variance | |||||
(Std.usage-actual usage)*Std.price | |||||
(12*2000-23000)*2 | |||||
2000 | (F) | ||||
Calculate the direct labor rate variance | |||||
(Std.price-actual price)*actual hours | |||||
(15-48000/4000)*4000 | |||||
12000 | (F) | ||||
Calculate the variable overhead efficiency variance. | |||||
(actual hours-Std.hrs)*Std.overhead rate | |||||
(1900-1950)*10 | |||||
-500 | (F) | ||||
Calculate the variable overhead spending | |||||
(10*1950) | |||||
19500 | |||||
Calculate the direct labor efficiency variance | |||||
(actual hours-Std.hrs)*Std.labor rate | |||||
(4000-2*1950)*15 | |||||
1500 | (A) | ||||
Get Answers For Free
Most questions answered within 1 hours.