Question

Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety...

Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 39%. When last calculated, Waymouth’s MCE was 34%.

Key measures from the recent month’s production, averaged over all the jobs during that period, are as follows:

Activity Average Time (hours)
New product development 28.0
Materials handling 1.5
Order setup 5.5
Machine maintenance 2.5
Order scheduling 2.0
Inspection of completed order 4.5
Pack and move to storage or ship 1.5
Manufacturing assembly 22.0
Order taking and checking 2.5
Receiving and stocking raw materials 5.5
Inspection of raw materials at start of production 1.5

Required:

Determine the manufacturing cycle efficiency (MCE) for the recent month. (Round your answer to 1 decimal place.)

Homework Answers

Answer #1
Manufacturing cycle efficiency (MCE) = Total processing time/Total cycle time
Manufacturing cycle efficiency (MCE) = 22/46.5= 47.3%
Workings:
Total processing time=Manufacturing assembly = 22.0
Cycle time:
Materials handling 1.5
Order setup 5.5
Machine maintenance 2.5
Order scheduling 2.0
Inspection of completed order 4.5
Pack and move to storage or ship 1.5
Manufacturing assembly 22.0
Receiving and stocking raw materials 5.5
Inspection of raw materials at start of production 1.5
Total Cycle time 46.5
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 31%. When last calculated, Waymouth’s MCE was 28%. Key measures from the recent month’s production,...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days)? ?...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT