The following data pertain to activity and utilities costs for
two recent years:
Year 2 |
Year 1 |
|
Activity Level in Units |
15,000 |
12,000 |
Utilities Cost |
$12,000 |
$8,000 |
Using the high-low method, what is the variable cost per unit
for utilities?
Select one:
a. $1.25 per unit.
b. $0.75 per unit.
c. $1.33 per unit.
d. $1.50 per unit.
Variable Cost per Unit = (Highest Activity Cost – Lowest Activity Cost)/ (Highest Activity Units – Lowest Activity Units)
Highest Activity Cost = 12000
Lowest Activity Cost = 8000
Highest Activity Units = 15000
Lowest Activity Units = 12000
Variable Cost per Unit = (12000-8000)/(15000-12000)
= 1.33 per unit