Question

Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...

Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow:

  Budgeted fixed factory overhead:
     Setup   $ 57,600   
     Other 265,000
$ 322,600
  Total factory overhead incurred $ 494,000
  Variable factory overhead rate:
     Per setup $ 650
     Per machine hour $ 4
  Total standard machine hours allowed for the units manufactured 24,000 hours
  Machine hours actually worked 28,000 hours
  Actual total number of setups 32
Required:
1.

Compute (a) the total overhead spending variance, (b) the overhead efficiency variance, and (c) the total overhead flexible-budget variance for 2016.

2. Assume that the company includes all setup costs as variable factory overhead. The budgeted total fixed overhead, therefore, is $265,000, and the standard variable overhead rate per setup is $2,250. What are the (a) overhead spending, (b) efficiency, and (c) flexible-budget variances for the year?

3.

Assume that the company uses only machine hours as the activity measure to apply both variable and fixed overhead, and that it includes all setup costs as variable factory overhead. What is the (a) overhead spending variance, (b) efficiency variance, and (c) flexible-budget variance for the year?

     

Homework Answers

Answer #1
Requirement
a Standard MH Per Unit
36000/7200
5
No of units manufactured
Standard allowed MH/Standard MH per unit
24000/5
4800
Budgeted no of units per set up
units/no of set up
7200/36
200 units /set up
Std no of set ups for units manufactured
4800/200
24
Therefore Spending variance
Variable OH +Fixed OH -Actual OH
VOH (32*650)+((28000*4)
Fixed OH $322,600
Actual OH $494,000
Therefore Spending variance
$455400-$494000
$38600 Unfavorable
b Efficiency Variance
(24*650)+(24000*4)+$322600-$455400
$434200-$455400
$21200 Unfavorable
c Flexible Budget Variance
Spending Variance +Efficiency variance
$21200+$38600
$59800 Unfavorable
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow:   Budgeted fixed factory overhead:      Setup   $ 57,600         Other 265,000 $ 322,600   Total factory overhead incurred $ 494,000   Variable factory overhead rate:      Per setup $ 650      Per machine hour $ 4   Total standard machine hours allowed for the units manufactured 24,000 hours   Machine hours actually worked 28,000 hours...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
Overhead Variances, Two- And Three-Variance Analyses Oerstman, Inc., uses a standard costing system and develops its...
Overhead Variances, Two- And Three-Variance Analyses Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 123,000 units requiring 492,000 direct labor hours. (Practical capacity is 512,000 hours.) Annual budgeted overhead costs total $772,440, of which $551,040 is fixed overhead. A total of 119,300 units using 490,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were...
Overhead Variances, Four-Variance Analysis, Journal Entries Laughlin, Inc., uses a standard costing system. The predetermined overhead...
Overhead Variances, Four-Variance Analysis, Journal Entries Laughlin, Inc., uses a standard costing system. The predetermined overhead rates are calculated using practical capacity. Practical capacity for a year is defined as 1,000,000 units requiring 200,000 standard direct labor hours. Budgeted overhead for the year is $750,000, of which $300,000 is fixed overhead. During the year, 900,000 units were produced using 190,000 direct labor hours. Actual annual overhead costs totaled $800,000, of which $294,700 is fixed overhead. Required: 1. Calculate the fixed...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following data pertain to October: Master budget data: Units 2,500 Total machine hours (denominator volume) 100,000 Total variable overhead cost $ 250,000 Total fixed overhead cost $ 50,000 Actual operating results: Variable overhead cost incurred $ 265,000 Fixed overhead cost incurred $ 54,000 Units manufactured 2,250 Total machine hours 96,000 Required: Compute the following variances using machine hours as the activity variable used to assign...
Capiz Corporation uses the two-way overhead variance analysis. During the recently ended period, total controllable variance...
Capiz Corporation uses the two-way overhead variance analysis. During the recently ended period, total controllable variance was determined to be at P16,000 unfavorable while total non-controllable variance was at P6,000 favorable. Total actual factory overhead amounted to P3,530,000. Actual production totaled 352,000 units while standard machine hours per unit produced is 2 hours. Total budgeted capacity is 700,000 machine hours. a. How much is the total overhead applied to actual production? b. What is the standard overhead rate per hour?...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4 per Ib.) $ 120.00 Direct labor (5 hrs. @ $14 per hr.) 70.00 Factory overhead—Variable (5 hrs. @ $8 per hr.) 40.00 Factory overhead—Fixed (5 hrs. @ $10 per hr.) 50.00 Total standard cost $ 280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,700 units, which...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT