Question

*PLEASE FINISH #2, any line with a "-----' needs to be completeled* Reynolds Printing Company specializes...

*PLEASE FINISH #2, any line with a "-----' needs to be completeled*

Reynolds Printing Company specializes in wedding announcements. Reynolds uses an actual job-order costing system. An actual overhead rate is calculated at the end of each month using actual direct labor hours and overhead for the month. Once the actual cost of a job is determined, the customer is billed at actual cost plus 50%.

During April, Mrs. Lucky, a good friend of owner Jane Reynolds, ordered three sets of wedding announcements to be delivered May 10, June 10, and July 10, respectively. Reynolds scheduled production for each order on May 7, June 7, and July 7, respectively. The orders were assigned job numbers 115, 116, and 117, respectively.

Reynolds assured Mrs. Lucky that she would attend each of her daughters' weddings. Out of sympathy and friendship, she also offered a lower price. Instead of cost plus 50%, she gave her a special price of cost plus 25%. Additionally, she agreed to wait until the final wedding to bill for the three jobs.

On August 15, Reynolds asked her accountant to bring her the completed job-order cost sheets for Jobs 115, 116, and 117. She also gave instructions to lower the price as had been agreed upon. The cost sheets revealed the following information:

Job 115 Job 116 Job 117
Cost of direct materials $250.00 $250.00 $250.00
Cost of direct labor (5 hours) 25.00 25.00 25.00
Cost of overhead 200.00 400.00 400.00
  Total cost $475.00 $675.00 $675.00
  Total price $593.75 $843.75 $843.75
Number of announcements 500 500 500

Reynolds could not understand why the overhead costs assigned to Jobs 116 and 117 were so much higher than those for Job 115. She asked for an overhead cost summary sheet for the months of May, June, and July, which showed that actual overhead costs were $20,000 each month. She also discovered that direct labor hours worked on all jobs were 500 hours in May and 250 hours each in June and July.

Required:

1. Explain how the overhead costs were assigned to each job.

May: $ 200

June and July: $ 400

2. Recompute the cost of each job and its price given your method of overhead cost assignment. If required, round your answers to the nearest cent.

Cost and price of each job:
Direct materials $250
Direct labor 25
Overhead --------
Total cost $-------
Plus 25% markup --------
Price $-----------

Which method do you think is best?
Predetermined rate

Homework Answers

Answer #1

In my personal opinion, the method used currently by Reynold is incorrect as he is using the rate of that current month while the customer contracted for the items in April only. There should be recorded pre determined overhead rate and the rate of May would be suitable for it when the firsrt order was executed. Accordingly,

Cost and price of each job:
Direct materials $250
Direct labor 25
Overhead 200
Total cost $ 475
Plus 25% markup $ 118.75
Price $593.75
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
5. Assume (1) a company’s plantwide predetermined overhead rate is $13.00 per direct labor-hour, and (2)...
5. Assume (1) a company’s plantwide predetermined overhead rate is $13.00 per direct labor-hour, and (2) its job cost sheet for Job X shows that this job incurred direct materials and direct labor charges of $500 and $360, respectively. If Job X’s total job cost is $1,289, how many direct labor-hours were worked on this job? 6. Assume (1) actual machine-hours worked during the period of 54,000 hours, (2) estimated machine-hours to be worked during the period of 55,600 hours,...
Concord Company manufactures custom-order furniture. During 2020, actual manufacturing overhead totaled $710000. Based on the 2020...
Concord Company manufactures custom-order furniture. During 2020, actual manufacturing overhead totaled $710000. Based on the 2020 results, and projected production for 2021, management prepared the 2021 budget and estimated that manufacturing overhead would total $1156900. The estimated number of direct labor hours for 2021 is 50300, and the estimated amount of direct labor cost is $1060000. The company plans to use direct labor hours as the basis to allocate overhead to jobs. During May and June 2021, employees worked on...
Exercise 2-3 Analysis of cost flows LO C2 As of the end of June, the job...
Exercise 2-3 Analysis of cost flows LO C2 As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 25,000 $ 48,000 $ 64,000 Direct labor 13,000 26,900 39,000 Overhead applied 4,810 9,953 14,430 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $3,800;...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows: Zayner Company is a job order costing company that uses activity-based costing (ABC) to apply manufacturing overhead to different jobs. Zayner identified three activities and the related cost drivers. The budgeted information (budget) for the year is as follows: Activity Cost Driver Amount of Driver Engineering...
Voltus Communications, a manufacturer of communications equipment, uses a job costing system. Manufacturing overhead is applied...
Voltus Communications, a manufacturer of communications equipment, uses a job costing system. Manufacturing overhead is applied based on machine hours and it uses a predetermined overhead rate with budgeted overhead of $3,600,000 for the year and 80,000 machine hours. Voltus uses a financial year of 1 July 2018 to 30 June 2019 and all the activities for the year have been carried out. Summarised details for period 1 July 2018 to 31 May 2019 and for June 2019 follow. Jobs...
1. Carrothers Company estimates that total factory overhead costs will be $960,000 for the year. Direct...
1. Carrothers Company estimates that total factory overhead costs will be $960,000 for the year. Direct labor hours are estimated to be 80,000. a. For Carrothers Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. ___________ per direct labor hour b. During August, Carrothers Company accumulated 4,300 hours of direct labor costs on Job 50 and 5,100 hours on Job 56. Determine the amount of factory overhead applied to Jobs 50 and 56 in...
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,700 and Job 94 with a beginning balance of $7,200. Jagjit applies overhead at the rate of $6 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...
During 2013, Arb Company incurred the following direct labor costs: January Php20,000 and February Php30,000. Arb...
During 2013, Arb Company incurred the following direct labor costs: January Php20,000 and February Php30,000. Arb uses a predetermined overhead rate of 120% of direct labor cost. Estimated overhead for the 2 months, respectively, totaled Php19,500 and Php35,700. Actual overhead for the 2 months, respectively, totaled Php24,500 and Php32,500. Instructions Determine if overhead is over- or underapplied for each of the two months and the respective amounts. Graham Manufacturing is a small manufacturer that uses machine-hours as its activity base...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT