Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799...

Slonaker Inc. has provided the following data concerning its maintenance costs:

Machine-Hours Maintenance
Cost
  April 5,799           $30,379        
  May 5,782           $30,289        
  June 5,764           $30,237        
  July 5,761           $30,233        
  August 5,717           $30,078        
  September 5,795           $30,360        
  October 5,809           $30,388        
  November 5,801           $30,378        
  December 5,785           $30,318        

Management believes that maintenance cost is a mixed cost that depends on machine-hours.

Required:

Estimate the variable cost per machine-hour and the fixed cost per month using the high-low method. (Round your answers to 2 decimal places. Omit the "$" sign in your response.)

Homework Answers

Answer #1
Variable Cost per machine hour = 3.37
Fixed Cost = 10,811.67
Machine-Hours Maintenance Cost
High 5809 $         30,388
Low 5717 $         30,078
Change 92 $               310
Variable Cost = Change in Cost / Change in Activity
= $310 / 92
= $              3.37 per machine hour
Fixed Cost element = Total Cost - Variable Cost element
= $30,388 - ($3.37 X 5,809)
= $   10,811.67
Alternatively, Fixed cost = $30,078 - ($3.37 X 5,717)
= $   10,811.71
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March...
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March 4,440 $50,950 April 4,431 $50,877 May 4,412 $50,696 June 4,460 $51,113 July 4,414 $50,711 August 4,433 $50,900 September 4,443 $50,976 October 4,415 $50,730 November 4,391 $50,530 Management believes that maintenance cost is a mixed cost that depends on machine-hours. Using the high-low method, calculate a. Variable cost per machine-hour b.  Fixed cost per month c. What would total costs be for a month with 4,000...
Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost March 4,214 $...
Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost March 4,214 $ 39,258 April 4,278 $ 39,613 May 4,319 $ 39,891 June 4,242 $ 39,414 July 4,298 $ 39,747 August 4,310 $ 39,808 September 4,235 $ 39,482 October 4,311 $ 39,821 November 4,233 $ 39,405 Halladay's Management has determined that the plant's electricity cost is a mixed cost that depends on machine-hours used at the plant. Required: Estimate the variable cost per machine-hour and the fixed...
Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost   March 4,214 $...
Electricity costs at Halladay Corporation’s manufacturing plant are listed below. Machine-Hours Utility Cost   March 4,214 $ 39,258   April 4,278 $ 39,613   May 4,319 $ 39,891   June 4,242 $ 39,414   July 4,298 $ 39,747   August 4,310 $ 39,808   September 4,235 $ 39,482   October 4,311 $ 39,821   November 4,233 $ 39,405 Halladay's Management has determined that the plant's electricity cost is a mixed cost that depends on machine-hours used at the plant. Required: Estimate the variable cost per machine-hour and the fixed...
Crane, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity...
Crane, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity Costs January 500 $240 February 540 $280 March 370 $190 April 470 $210 May 670 $260 June 710 $330 July 300 $170 August 520 $280 September 260 $140 October 740 $340 November 860 $350 December 600 $320 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. Using the high-low method, compute the variable...
Cullumber Corp. has collected the following data concerning its maintenance costs for the past 6 months....
Cullumber Corp. has collected the following data concerning its maintenance costs for the past 6 months. Units Produced Total Cost July 20,190 $44,085 August 35,904 53,856 September 40,392 61,710 October 24,684 47,358 November 44,880 83,589 December 42,636 69,564 (a1) Compute the variable cost per unit using the high-low method. (Round answer to 2 decimal places, e.g. 2.25.) Variable cost per unit    (a2) Compute the fixed cost elements using the high-low method. Fixed costs
Colombia Company has provided the following data for maintenance cost: Prior Year Current Year   Machine hours...
Colombia Company has provided the following data for maintenance cost: Prior Year Current Year   Machine hours 18,000        20,300          Maintenance cost $34,700        $37,460        Maintenance cost is a mixed cost with variable and fixed components. The fixed and variable components of maintenance cost are closest to: rev: 12_20_2016_QC_CS-72978 $13,100 per year plus $.833 per machine hour $24,360 per year plus $.833 per machine hour $13,100 per year plus $1.20 per machine hour $34,700 per year plus $1.20 per...
Oriole, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity...
Oriole, Inc., has collected the following information on its cost of electricity: Machine Hours Total Electricity Costs January 500 $240 February 540 $300 March 370 $210 April 440 $220 May 680 $290 June 730 $330 July 330 $180 August 530 $260 September 230 $118 October 740 $340 November 860 $370 December 600 $340 Using the high-low method, compute the variable cost of electricity per machine hour. (Round unit cost to 2 decimal places, e.g. 52.75.) Variable cost $   per machine hour...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows:...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows: Month Electricity Costs Machine Hours January $12,600 8000 February 14,333 9600 March 9,333 5600 April 15,667 10200 May 19,167 9200 June 15,134 13200 July 16,834 14400 August 15,500 12000 September 10,667 6000 October 17,667 13200 November 21,000 16800 Required: a. Using the high-low method, develop an estimate of variable electricity costs per machine hour. b. Using the high-low method, develop an estimate of fixed...
The following information is available for a company’s maintenance cost over the last twelve months: Month...
The following information is available for a company’s maintenance cost over the last twelve months: Month Maintenance Hours Maintenance Cost January 43 $43,820 February 38 $45,010 March 35 $44,000 April 31 $45,000 May 36 $43,200 June 28 $38,760 July 18 $32,300 August 19 $35,440 September 25 $37,500 October 29 $39,560 November 34 $42,100 December 39 $46,700 Based on the high-low method, what is the variable and fixed cost component of total maintenance cost? Variable cost per unit: $ Fixed cost:...
Ivanhoe Corp. has collected the following data concerning its maintenance costs for the past 6 months....
Ivanhoe Corp. has collected the following data concerning its maintenance costs for the past 6 months. Units Produced Total Cost July 18,700 $39,712 August 33,344 50,016 September 37,512 57,310 October 22,924 40,126 November 41,680 77,629 December 39,596 64,604 Part 1 Compute the variable cost per unit using the high-low method. (Round answer to 2 decimal places, e.g. 2.25.) Variable cost per unit $enter the variable cost per unit in dollars rounded to 2 decimal places eTextbook and Media Assistance Used...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT