Question

Lydia Company planned to produce 12,000 units. Processing required 16,000 machine hours at a cost of...

Lydia Company planned to produce 12,000 units. Processing required 16,000 machine hours at a cost of $43,000 + $12 per machine hour. Actual sales were 15,000 units requiring 20,000 machine hours. Actual processing cost was $253,000.

_____ is the static-budget variance for processing.

Group of answer choices

$18,000 unfavorable

$30,000 unfavorable

$30,000 favorable

$18,000 favorable

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead cost to outputs: Actual total overhead cost incurred $ 24,000 Actual fixed overhead cost incurred $ 10,000 Budgeted fixed overhead cost $ 11,000 Actual machine hours 5,000 Standard machine hours allowed for the units manufactured 4,800 Denominator level — machine hours 5,500 Standard variable overhead rate per machine hour $ 3.00 What is variable overhead spending variance? Group of answer choices $960 favorable $1,000...
The following data were drawn from the records of Perez Corporation. Planned volume for year (static...
The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) 3,000 units Standard direct materials cost per unit 2.30 pounds @ $ 1.60 per pound Standard direct labor cost per unit 2.20 hours @ $ 3.50 per hour Total expected fixed overhead costs $ 13,200 Actual volume for the year (flexible budget) 3,200 units Actual direct materials cost per unit 1.80 pounds @ $ 2.20 per pound Actual direct labor cost per unit...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the most recent month: Machine-hour standard: Two machine hours per unit Standard fixed overhead rate: $20 per machine hour Actual production: 15,000 units Under-applied fixed overhead: $50,000 Fixed overhead budget variance: $30,000 favorable The budgeted fixed overhead and the fixed overhead volume variance, respectively, are $620,000 and $20,000 $680,000 and -$80,000 $650,000 and $50,000...
The following information for the past year is available from Thinnews Co., a company that uses...
The following information for the past year is available from Thinnews Co., a company that uses machine hours to apply standard factory overhead cost to outputs: Actual total factory overhead cost incurred $ 30,000 Actual fixed overhead cost incurred $ 7,000 Budgeted fixed overhead cost $ 12,000 Actual machine hours 8,000 Standard machine hours allowed for the units manufactured 4,600 Denominator volume—machine hours 7,500 Standard variable overhead rate per machine hour $ 3 The variable overhead spending variance, to the...
McKenna Company planned to produce 900 units during April with a total overhead budget of $12,400.  ...
McKenna Company planned to produce 900 units during April with a total overhead budget of $12,400.   However, while manufacturing the 1,000 units the microcomputer that contained the month's cost information broke down. With the computer out of commission, the accountant has been unable to complete the variance analysis report. The information missing from the report is lettered in the following set of data: Variable overhead: Standard cost per unit: 0.4 labour hour at $4 per hour Actual costs: $2,100 for...
Answer the following questions (#25 and #26) using the information below: Jenny's Corporation manufactured 26,000 grooming...
Answer the following questions (#25 and #26) using the information below: Jenny's Corporation manufactured 26,000 grooming kits for horses during March. The fixed-overhead cost-allocation rate is $20 per machine-hour. The following fixed overhead data pertain to March:                                                                          Actual      Static Budget Production                                               26,000 units         24,000 units Machine-hours                                         6,100 hours          6,000 hours Fixed overhead costs                                   $126,000              $120,000 What is the fixed overhead spending variance? A. $6,000 unfavorable B. $2,000 unfavorable C. $4,000 favorable D. $10,000 favorable Jenny's Corporation manufactured 26,000 grooming kits for...
Kenney Co. uses a standard cost system. Standard direct labor hours are the basis for applying...
Kenney Co. uses a standard cost system. Standard direct labor hours are the basis for applying overhead to production. The fixed overhead budget for the year is $450,000 and the expected activity level was 30,000 hours. Each unit of product is expected to use 2 hours of direct labor. Actual production was 14,500 units and the actual fixed overhead cost was $420,000. Required: Be sure to label each variance as F – favorable or U – unfavorable 1. What is...
Winle Corp has a standard cost system and applies overhead based on direct labor hours. The...
Winle Corp has a standard cost system and applies overhead based on direct labor hours. The standards for manufacturing overhead are as follow: Standard labor hours per unit of product 1.4 Standard manufacturing overhead cost 22.00 per hour During the current period, Winle worked 1,500 hours to produce 1,000 units. Total actual manufacturing overhead cost was $30,000. What was the manufacturing overhead rate variance for the month? Multiple Choice $800 Unfavorable $3,000 Favorable $3,000 Unfavorable $800 Favorable
Factory Overhead Controllable Variance Bellingham Company produced 6,400 units of product that required 3.5 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 6,400 units of product that required 3.5 standard hours per unit. The standard variable overhead cost per unit is $5.80 per hour. The actual variable factory overhead was $135,250. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $ Factory Overhead Volume Variance Dvorak Company produced 2,400 units of product that required 4 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 4,300 units of product that required 8.5 standard hours...
Factory Overhead Controllable Variance Bellingham Company produced 4,300 units of product that required 8.5 standard hours per unit. The standard variable overhead cost per unit is $6.00 per hour. The actual variable factory overhead was $210,970. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $ Favorable