a. Prob(line works) = .99 × .96 × .93 = .8839
#1:
Prob(line works) + Prob(line fails) × Prob(backup works)
= .8839 + [(1 - .8839) × (.8839)] = .9865
#2:
Prob:
.99 + [(1 - .99) × .99] = .9999
.96 + [(1 - .96) × .96] = .9984
.93 + [(1 - .93) × .93] = .9951
Overall: .9999 × .9984 × .9951 = .9934
Plan 2 is better (.9934 > .9865)
b.
In #1 the system will fail if any one of original and any one of backup machines fail.
In #2 the system will fail if any one of original and its backup machine both fail.
So, overall failing is more likely for #1.