Question

Microsoft Inc. has large overheads in their headquarters at Seattle. Microsoft applies overhead based on direct...

Microsoft Inc. has large overheads in their headquarters at Seattle. Microsoft applies overhead based on direct labor hours. The variable overhead standard is 8 hours at $3.70 per hour. During October, Microsoft Company spent $158,700 for variable overhead. 46,440 labor hours were used to produce 6,300 units. What is the variable overhead rate variance for Microsoft?

Homework Answers

Answer #1

Actual Rate = Actual Variable Overhead Cost / Actual Hours Used
                   = $158,700 / 46,440

Variable Overhead rate variance
            = (Standard Rate - Actual Rate) x Actual Hours
           = ($3.70 - 158700 / 46440) x 46,440
           = $13,128 Favorable

          

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Nguyen Inc. applies overhead to products based on direct labor hours using normal costing. During 2016,...
Nguyen Inc. applies overhead to products based on direct labor hours using normal costing. During 2016, total overhead costs were estimated to be $500,000. Actual overhead totaled $540,000 based on 32,000 actual direct labor hours. At the end of the year, overhead was overapplied by $20,000. Based on this information, what was the predetermined overhead rate used during 2016? $16.88 per direct labor hour. $16.25 per direct labor hour. $15.63 per direct labor hour. $17.50 per direct labor hour. None...
Winle Corp has a standard cost system and applies overhead based on direct labor hours. The...
Winle Corp has a standard cost system and applies overhead based on direct labor hours. The standards for manufacturing overhead are as follow: Standard labor hours per unit of product 1.4 Standard manufacturing overhead cost 22.00 per hour During the current period, Winle worked 1,500 hours to produce 1,000 units. Total actual manufacturing overhead cost was $30,000. What was the manufacturing overhead rate variance for the month? Multiple Choice $800 Unfavorable $3,000 Favorable $3,000 Unfavorable $800 Favorable
Q7. Trini Inc. bases its manufacturing overhead budget on budgeted direct labor-hours. The direct labor budget...
Q7. Trini Inc. bases its manufacturing overhead budget on budgeted direct labor-hours. The direct labor budget indicates that 9,100 direct labor-hours will be required in May. The variable overhead rate is $2.60 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $100,440 per month, which includes depreciation of $8,910. All other fixed manufacturing overhead costs represent current cash flows. The May cash disbursements for manufacturing overhead on the manufacturing overhead budget should be? Q8. The following data pertains to...
Haylock Inc. bases its manufacturing overhead budget on budgeted direct labor-hours. The direct labor budget indicates...
Haylock Inc. bases its manufacturing overhead budget on budgeted direct labor-hours. The direct labor budget indicates that 7,400 direct labor-hours will be required in August. The variable overhead rate is $1.60 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $100,400 per month, which includes depreciation of $8,950. All other fixed manufacturing overhead costs represent current cash flows. The August cash disbursements for manufacturing overhead on the manufacturing overhead budget should be: Multiple Choice $11,840 $103,290 $112,240 $91,450 3....
DTE Inc. uses direct labor hours as a basis for charging standard overhead to work in...
DTE Inc. uses direct labor hours as a basis for charging standard overhead to work in process. The annual standard overhead rate is based on budgeted variable overhead of $840,000 and budgeted fixed overhead at $700,000, and a budget of 150,000 hours to produce 50,000 units. During the month of March, 4500 units were produced. Actual Fixed overhead was $52,000 and actual variable overhead was $26,000. Determine the standard overhead cost per direct labor hour. Compute the standard overhead cost...
Xcel Technologies, Inc. applies variable manufacturing overhead to products based on machine hours. The standard variable...
Xcel Technologies, Inc. applies variable manufacturing overhead to products based on machine hours. The standard variable overhead rate is $5 per machine hour. The standard time allowed for producing one unit is 2 machine hours. During the month of August, the company produced 500 units. It incurred actual variable costs of $5,655 and used 870 machine hours. Calculate the variable overhead efficiency variance for the month of August. A) $650 favorable B) $650 unfavorable C) $845 favorable D) $845 unfavorable
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
1) Pardoe Inc., manufactures a single product in which variable manufacturing overhead is assigned on the...
1) Pardoe Inc., manufactures a single product in which variable manufacturing overhead is assigned on the basis of standard direct labor-hours. The company uses a standard cost system and has established the following standards for one unit of product: Standard Quantity Standard Price or Rate Standard Cost Direct materials 1.5 pounds $3.00 per pound $4.50 Direct labor 0.6 hours $6.00 per hour $3.60 Variable manufacturing overhead 0.6 hours $1.25 per hour $0.75 During March, the following activity was recorded by...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT