Q1:
The standard costs and actual costs for direct materials for the manufacture of 2,600 actual units of product are
Standard Costs | |
Direct materials (per completed unit) | 1,040 kilograms @$8.61 |
Actual Costs |
|
Direct materials | 2,600 kilograms @ $8.20 |
Round your final answer to the nearest dollar.
The amount of direct materials price variance is
$426 favorable
$426 unfavorable
$1,066 favorable
$1,066 unfavorable
Q2:
The standard costs and actual costs for direct materials for the manufacture of 2,650 actual units of product are
Standard Costs | |
Direct materials | 2,650 kilograms @$8.60 |
Actual Costs |
|
Direct materials | 2,700 kilograms @ $8.05 |
The amount of the direct materials quantity variance is
$430 unfavorable
$430 favorable
$344 favorable
$344 unfavorable
Q3:
The Flapjack Corporation had 8,200 actual direct labor hours at
an actual rate of $12.40 per hour. Original production had been
budgeted for 1,100 units, but only 1,000 units were actually
produced. Labor standards were 7.6 hours per completed unit at a
standard rate of $13.00 per hour.
The labor rate variance is
a.$4,920 favorable
b.$4,920 unfavorable
c.$4,560 unfavorable
d.$4,560 favorable
Q4:
The Flapjack Corporation had 8,200 actual direct labor hours at
an actual rate of $12.40 per hour. Original production had been
budgeted for 1,100 units, but only 1,000 units were actually
produced. Labor standards were 7.6 hours per completed unit at a
standard rate of $13.00 per hour.
The labor time variance is
a.$9,880 favorable
b.$9,880 unfavorable
c.$7,800 favorable
d.$7,800 unfavorable
1) The amount of direct materials price variance is =
(Standard Rate per kg - Actual Rate per kg)* Actual Quantity
=(8.61-8.2)2600 = (1066) unfavourable.
2) The amount of the direct materials quantity variance is=
(Standard Quantity for Actual Production - Actual Qunatity)*Standard Rate
=(2650-2700)*8.6 = (430) Unfavourable
3) The labor rate variance is =
(Standard Rate per hour - Actual Rate per hour) * Actual Hours Worked
= (13-12.4)*8200 = 4920 Favourable
4) The labor time variance is
( Standard Hour for Actual Production - Actual Hour) *Standard Rate
= [ (1000*7.6) - (8200) ] * 13
= (7800) Unfavourable
Get Answers For Free
Most questions answered within 1 hours.