Question

Compute for the missing amount. The total maintenance costs of Silver Company in the last four...

Compute for the missing amount.

The total maintenance costs of Silver Company in the last four months are presented below:

Month Machine hours                        Maintenance cost

                January                    7, 200                                      P450, 000

                February                  6, 800                                      P422, 000

                March                      7, 000                                      P440, 000

                April                        6, 400                                      P418, 000

Requirements:

a.Variable cost per machine hour

b. Total fixed cost

c.Budgeted maintenance cost in May if the company is planning to use 7, 500 hours.

d. Budgeted maintenance cost in May if the company is planning to use 8, 000 hours.

Homework Answers

Answer #1

Hope it helps. In case of any doubts or issues, please do comment below

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Ken-Ken Company has determined that their maintenance cost is a mixed cost and aims to perform...
Ken-Ken Company has determined that their maintenance cost is a mixed cost and aims to perform segregation technique. They observed the maintenance cost over a six-month period according to behavior with machine hours, their main cost driver. Use high-low method and compute the following below. Month Maintenance Cost Machine Hours January 5,400.00   900.00 February 6,000.00 1,050.00 March 7,200.00 1,500.00 April 9,000.00 2,070.00 May 6,400.00 1,200.00 June 11,000.00 2,100.00 1. Variable cost rate per hour 2. Fixed cost 3. Expected total...
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March...
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March 4,440 $50,950 April 4,431 $50,877 May 4,412 $50,696 June 4,460 $51,113 July 4,414 $50,711 August 4,433 $50,900 September 4,443 $50,976 October 4,415 $50,730 November 4,391 $50,530 Management believes that maintenance cost is a mixed cost that depends on machine-hours. Using the high-low method, calculate a. Variable cost per machine-hour b.  Fixed cost per month c. What would total costs be for a month with 4,000...
The accountant of ABC Company has the following maintenance costs and working hours for the past...
The accountant of ABC Company has the following maintenance costs and working hours for the past five months and trying to separate the cost to its components: Month Cost Working hours March $100,000 5,000 April 60,000 1,000 May 68,600 2,000 June 83,450 3,420 July 88,000 5,250 what is the variable cost per hour? [[selectone]] a. $16 per hour b. $14 per hour c. $10 per hour d. $12 per hour
Silver Company makes a product that is very popular as a Mother’s Day gift. Thus, peak...
Silver Company makes a product that is very popular as a Mother’s Day gift. Thus, peak sales occur in May of each year, as shown in the company’s sales budget for the second quarter given below: April May June Total   Budgeted sales (all on account) $380,000     $580,000     $200,000     $1,160,000 From past experience, the company has learned that 20% of a month’s sales are collected in the month of sale, another 60% are collected in the month following...
The controller of Concord Industries has collected the following monthly expense data for use in analyzing...
The controller of Concord Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,970 300 February 3,020 360 March 3,620 510 April 4,520 680 May 3,220 510 June 6,130 700 (a1) Determine the variable cost components using the high-low method. (Round variable cost to 2 decimal places e.g. 12.25.) Variable cost per machine hour $
The Silver Company manufacturers two products, the Scrambler and Organizer. Direct labor, Direct material, and total...
The Silver Company manufacturers two products, the Scrambler and Organizer. Direct labor, Direct material, and total overhead costs are given. The company uses predetermined overhead rates (POHR) to allocate overhead. Certain overhead items are associated with Machine Hours and other items are associated with Direct Labor Cost. This is shown in the overhead categories below.    Scrambler                          Organizer                                                     Units produced 400 900                                             Direct labor cost                       $150,000                            $230,000 Direct material Cost                 $ 80,000                            $225,000                 Direct labor hours 6,000 9,000 Machine hours                             ...
Fosnight Enterprises prepared the following sales? budget: Month Budgeted Sales March $ 9 comma 000$9,000 April...
Fosnight Enterprises prepared the following sales? budget: Month Budgeted Sales March $ 9 comma 000$9,000 April $ 15 comma 000$15,000 May $ 13 comma 000$13,000 June $ 12 comma 000$12,000 The expected gross profit rate is 2020?% and the inventory at the end of February was $ 12 comma 000$12,000. Desired inventory levels at the end of the month are 1010?% of the next? month's cost of goods sold. What is the budgeted cost of goods sold for? May? Brittany...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $173,870        May 39,000    $151,570        June 59,000    $196,170        July 69,000    $218,470   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 42,900     Supervisory salaries (fixed) 46,000   Maintenance (mixed) 62,670   Total overhead cost $ 151,570 The...
Johanson Company has provided the following data for the first five months of the year: Machine...
Johanson Company has provided the following data for the first five months of the year: Machine Hours Lubrication Cost January 120 $750 February 160 $800 March 200 $870 April 150 $790 May 170 $840 Using the High Low Method, compute the expected cost at 140 Machine Hours.
Silver Company makes a product that is very popular as a Mother’s Day gift. Thus, peak...
Silver Company makes a product that is very popular as a Mother’s Day gift. Thus, peak sales occur in May of each year, as shown in the company’s sales budget for the second quarter given below: April May June Total Budgeted sales (all on account) $400,000 $600,000 $190,000 $1,190,000 From past experience, the company has learned that 30% of a month’s sales are collected in the month of sale, another 60% are collected in the month following sale, and the...