The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,102. A total of 41 direct labor-hours and 197 machine-hours were worked on the job. The direct labor wage rate is $23 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $25 per machine-hour. The total cost for the job on its job cost sheet would be: |
Multiple Choice
$4,926
$10,115
$7,970
$5,345
Option 3rd is correct.i.e $7,970
Particulars | Workings | Amount($) |
Direct Material | - | 2,102 |
Direct Labor | 41 direct labor-hours * $23.00 per labor-hour | 943 |
Manufacturing overhead | 197 machine-hours * $25.00 per machine-hour | 4,925 |
Total cost | 7,970 |