Question

Under a job order costing system, the dollar amount of the entry involved in the transfer...

Under a job order costing system, the dollar amount of the entry involved in the transfer of goods from work-in-process inventory to finished goods inventory is the total of the costs charged to all jobs

A) started during the period

B) completed during the period

C) completed and sold during the period

D) started and completed during the period

Which of the following would not be an appropriate allocation base for assigning utility costs for heating three separate product line production departments?

A) sales generated by each department

B) square footage used by each department

C) machine hours used by each department

D) kilowatt hours used by each department

Homework Answers

Answer #1

The correct answer is Option B.

The entry reflects the transfer of the cost of the jobs that are completed during the period irrespective of whether it was started during that period or not. So implying that even if it was started during that period and it did not finish, it will not be transferred to finished goods. Hence Option A is inccorrect.

The goods that are completed and sold during the period will be recorded as cost of goods sold. Hence Option C is incorrect.

The work-in process can have a opening balance of jobs that are already started, hence such jobs may also finish during the period, hence those will also be transfered. Hence, it can not be said that the entry will reflect only those jobs that are started and completed during the period. Hence, Option D is incorrect.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
JOB ORDER COSTING PROBLEM        During May, $42,000 of direct materials were used on Job #...
JOB ORDER COSTING PROBLEM        During May, $42,000 of direct materials were used on Job # 24, 320 hours of       direct labor were charged at a rate of $25 per hour, and manufacturing       overhead was applied at a rate of 75 % of direct labor costs. Job # 24 was       completed during May and transferred to Finished Goods Inventory. What is the total cost of Job # 24? Prepare the journal entries to record the addition of...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $110,500 of manufacturing overhead for an estimated allocation base of $85,000 direct material dollars to be used in production. The company has provided the following data for the just completed year:         Purchase of raw materials $...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 16,500 $ 9,300 $ 0...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 19,500 $ 12,300 $ 0...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
1. The overhead cost applied to a job during a period is recorded with a credit...
1. The overhead cost applied to a job during a period is recorded with a credit to Factory Overhead and a debit to: Multiple Choice Jobs Overhead Expense. Cost of Goods Sold. Finished Goods Inventory. Indirect Labor. Work in Process Inventory. 2. Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the...
ABC Company began operations during 2022 and employs a job-order costing system with departmental overhead rates....
ABC Company began operations during 2022 and employs a job-order costing system with departmental overhead rates. Overhead from both Department A and Department B is assigned to jobs on the basis of direct labor hours. Below is a summary of events and transactions that occurred during 2022: a. ABC Company had the following estimates for 2022: Dept. A Dept. B Total Overhead cost $136,500 $192,000 $328,500 Direct labor hours 14,000 16,000 30,000 b. ABC Company began work on three jobs....
The Lee Corporation uses a job-order costing system. The following data were recorded for June: June...
The Lee Corporation uses a job-order costing system. The following data were recorded for June: June 1 Added During June Job Number Work in Process Inventory Direct Materials Direct Labor 235 $2,600 $640 $430 236 $1,600 $860 $1,070 237 $1,090 $1,280 $1,870 238 $850 $1,640 $2,410 Overhead is charged to production at 65% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and 238 have been delivered to customers....
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 50,000 Work in process $ 30,800 Finished goods $ 43,200 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $12.00 per direct labor-hour was based on a cost formula that estimated $480,000 of total manufacturing overhead for an estimated activity level of 40,000 direct...