SmallCo, which has a cost of capital of 12%, is considering the following project:
Year | 0 | 1 | 2 | 3 |
Cash flows of project | $(2,000) | $1,000 | $800 | $700 |
What is the NPV of the project?
Select one:
a. $29
b. $700
c. $500
d. $2,029
Net present value = $29
Working notes for the above answer is as under
NPV calculation |
|||||
i |
12% |
||||
Year |
Cash Flow (A) |
x |
PV Factor (B) I= 12% |
= |
Prasent Value (C=A*B) |
1 |
1,000 |
x |
0.893 |
893 |
|
2 |
800 |
x |
0.797 |
637.6 |
|
3 |
700 |
x |
0.712 |
498.4 |
|
Present Value of Cash inflow |
2029.00 |
||||
Present Value of Cash Outflow |
-2000.00 |
||||
Net present value (2029-2000) |
29 |