Question

Sharon Ltd has in the past ordered raw material T in quantities of 3,000 units which...

Sharon Ltd has in the past ordered raw material T in quantities of 3,000 units which is half a year’s supply. Management has instructed you, an inventory cost consultant, to advise them as to the most desired order quantities. The factory closes for 4 weeks annual leave per annum.

You are given the following data:

Inventory usage rate: 125 per week, Lead time: 3 weeks

Unit price: $1.50, Annual requirement: 6,000 units

Order cost: $9.00 per order, Carrying cost: $0.30 per unit per year Required:

Calculate the economic order quantity.

Calculate the reorder point.

How much would the company save by using this new method? (Assume the order point calculated in part b is used)

Solution:

For Requirement (a) formula is already provided in lecture slide.

For Requirement (b): Re-Order point = Lead time usage (No of weeks * Usage per week) For Requirement (c): Savings per year by ordering at EOQ (= Existing policy – EOQ policy) Existing policy = Cost of ordering + Cost of holding + safety stock

Cost of ordering = No of orders per annum * Cost of an order

Cost of holding = Average Inventory * Carrying cost per unit per annum Safety Stock = Usage per week * Lead Time * Carrying cost

EOQ policy = Cost of ordering + Cost of holding + Safety stock

For Requirement (c): Savings per year by ordering at EOQ (= Existing policy – EOQ policy)

Homework Answers

Answer #1

Ans: )

A.) Economic order quantity = square root of [(2 x Annual demand x ordering costs) ÷ carrying costs]

= square root of [(2 x (48 x 125) x 9) ÷ 0.3]

= square root of [32,400]

= 180 Units

B.) Re-Order point = Lead time usage (No of weeks * Usage per week)

= 3 weeks x 125 units

= 375 Units

C.) Cost Comparison

Existing Policy

New Policy

Order Size

3,000 Units

180 Units

No. of Orders

= (48 x 125) ÷ order Size

3,000 Units

180 Units

Ordering Cost

= No of orders * Cost of an order

$ 18

$ 306

Holding Cost

= Avg. Inventory * Carrying cost per unit

$ 450

$ 27

Total Cost

$ 468

$ 333

Total Cost Savings by EOQ (New method) = 468 – 333 =$ 135

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Exercise 10-1 (from Text 15.24) Economic order quantity The calculation of an Economic Order Quantity uses...
Exercise 10-1 (from Text 15.24) Economic order quantity The calculation of an Economic Order Quantity uses a formula which balances the cost of ordering stock (PER ORDER which may include research, account handling, supplier meetings and processing time AND if imported, import duties and customs clearance fees etc.) against the UNIT cost of holding inventory (these costs may include warehouse rent, insurance, storage costs etc.). The EOQ is the point where the two costs are equally balanced such that it...
A company orders a particular raw material in order quantities of 250 units. No safety stack...
A company orders a particular raw material in order quantities of 250 units. No safety stack is held, the stock holding cost is GHc 3.00 per unit per annum and the annual demand of 2,500 units. What is the total annual stock holding cost of the material?
Alexis Company uses 800 units of a product per year on a continuous basis. The product...
Alexis Company uses 800 units of a product per year on a continuous basis. The product has a fixed cost of $50 per order, and its carrying cost is $2 per unit per year. It takes 5 days to receive a shipment after an order is placed. And the firm wishes to hold 10 days usage in inventory as a safety stock Calculate the EOQ Determine the average level of inventory. (Note: Use a 365 day year to calculate daily...
URGENT Ltd uses the Economic Order Quantity Model to determine order quantities. The following information is...
URGENT Ltd uses the Economic Order Quantity Model to determine order quantities. The following information is given for the next year:                                                 Order costs                         20 per order                 Delivery costs                    5 per order                 Holding costs                     10% of purchase price per annum                 Annual demand                27,000 units                 Purchase price                  40 per unit                 No safety stocks are held.                                                                                                              a. What is the EOQ?                                      b. What are the total annual costs of stock if the company uses EOQ...
(URGENT ) PoMA Ltd uses the Economic Order Quantity Model to determine order quantities. The following...
(URGENT ) PoMA Ltd uses the Economic Order Quantity Model to determine order quantities. The following information is given for the next year:                                                Order costs                         20 per order                 Delivery costs                    5 per order                 Holding costs                     10% of purchase price per annum                 Annual demand                18,000 units                 Purchase price                  40 per unit                 No safety stocks are held.                                                                                                            a. What is the EOQ?                                     b. What are the total annual costs of stock if the company...
Knutson Products Inc. is involved in the production of airplane parts and has the following​ inventory,...
Knutson Products Inc. is involved in the production of airplane parts and has the following​ inventory, carrying, and storage​ costs: 1. Orders must be placed in round lots of 100 units. 2. Annual unit usage is150,000. ​(Assume a​ 50-week year in your​ calculations.) 3. The carrying cost is 25 percent of the purchase price. 4. The purchase price is ​$10 per unit. 5. The ordering cost is ​$200 per order. 6. The desired safety stock is 4000 units.​ (This does...
16) For supply item ABC, Andrews Company has been ordering 125 units based on the recommendation...
16) For supply item ABC, Andrews Company has been ordering 125 units based on the recommendation of the salesperson who calls on the company monthly. A new purchasing agent has been hired by the company who wants to start using the economic-order-quantity method and its supporting decision elements. She has gathered the following information: Annual demand in units 250 Days used per year 250 Lead time, in days 10 Ordering costs $100 Annual unit carrying costs $20 Required: Determine the...
A product has a reorder point of 110 units, and is ordered four times a year....
A product has a reorder point of 110 units, and is ordered four times a year. The following table shows the historical distribution of demand values observed during the reorder period. Demand Probability 100 .3 110 .4 120 .2 130 .1 Managers have noted that stockouts occur 30 percent of the time with this policy, and question whether a change in inventory policy, to include some safety stock, might be an improvement. The managers realize that any safety stock would...
Question 4: The following information pertains to raw material ‘A’ used in production process of Part...
Question 4: The following information pertains to raw material ‘A’ used in production process of Part Pearl Inc., Normal usage 50 tons per week Maximum usage 75 tons per week Minimum usage 25 tons per week Re-ordering Quantity30 unit Re-order period (Lead Time) 4 to 6 weeks You are required to calculate for Raw material A: (a) Re-order Stock Level (b) Minimum Stock Level (c) Average stock level; and (d) Maximum stock level
Ross White’s machine shop uses 2500 brackets during the course of a year, and this usage...
Ross White’s machine shop uses 2500 brackets during the course of a year, and this usage is relatively constant throughout the year. These brackets are purchased from a supplier 100 miles away for $15 each, and the lead time is 2 days. The holding cost per bracket per year is $1.50 (or 10% of the unit cost) and the ordering cost per order is $18.75. There are 300 working days per year. 1. Develop a total cost model for this...