Question

Question text Kerin Company produces a range of Biomedical products for industries. It uses a job-costing...

Question text

Kerin Company produces a range of Biomedical products for industries. It uses a job-costing system to calculate the cost of a particular job. Materials and labors used in the manufacturing process are direct in nature, but manufacturing overhead is allocated to different jobs using direct manufacturing labor costs. Kerin provides the following information:

Budget for 2019

Actual Results for 2019

Direct material costs

$ 5,500,000

$6,000,000

Direct manufacturing labor costs

    3,660,000

   4,500,000

Manufacturing overhead costs

    6,588,000

   7,560,000

Required:

1.      Compute the actual and budgeted manufacturing overhead rates for 2019.

2.      During March, the job-cost records for Job 666 contained the following information:

Direct materials used                                      $147,000

Direct manufacturing labor costs                    $102,000

Compute the cost of Job 666 using normal costing.

3.      At the end of 2019, compute the under-allocated or over-allocated manufacturing overhead using normal costing.

Homework Answers

Answer #1

1.

Budgeted Rate=
$6,588,000/$3,660,000= $1.80/dollar of labor cost

Actual Rate=
$7,560,000/$4,500,000= $1.68/dollar of labor cost

2.

Normal Costing (only difference is you take budgeted rate multiplied by the actual labor costs):

$6,588,000/$3,660,000= $1.80/dollar of labor cost

DM=$1,47,000
DL=$1,02.000
FOH=($1,02,000x$1.80)=$1,83,600

Total= $ 4,32,600

3.

Cr. for Applied Overhead ($1.80x$4,500,000)=$8,100,000

Db. for Actual Incurred (given)=$7,560,000

Result: Cr. balance of $540, 000 (Over applied FOH)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Somerset Products uses a job costing system with two direct cost categories and one manufacturing overhead...
Somerset Products uses a job costing system with two direct cost categories and one manufacturing overhead cost pool. Somerset allocates manufacturing overhead costs using direct manufacturing labor costs. The following information pertains to the year 2018: Budget Actual Direct material costs $2,150,000 $2,075,000 Direct manufacturing labor costs $1,750,000 $1,690,000 Manufacturing overhead costs $3,062,500 $3,211,000 The following information pertains to Job GWH undertaken in May 2018: Budget Actual Direct materials used $35,000 $35,000 Direct manufacturing labor costs $25,000 $30,000 a. Compute...
The Kristopher Company uses a job-costing system at its plant. The plant has a Machining Department...
The Kristopher Company uses a job-costing system at its plant. The plant has a Machining Department and an Assembly Department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the Machining Department overhead, allocated to jobs based on actual machine-hours, and the Assembly Department overhead, allocated to jobs based on actual direct manufacturing labor cost). The 2019 budget for the plant is: Machining Assembly Manufacturing overhead $1,800,000 $3,600,000 Direct manufacturing...
The Maclin Company uses a​ job-costing system at its​ Dover, Delaware, plant. The plant has a...
The Maclin Company uses a​ job-costing system at its​ Dover, Delaware, plant. The plant has a machining department and a finishing department. Maclin uses normal costing with two​ direct-cost categories​ (direct materials and direct manufacturing​ labor) and two manufacturing overhead cost pools​ (the machining department with​machine-hours as the allocation base and the finishing department with direct manufacturing labor costs as the allocation​ base). The 2017 budget for the plant is as​follows: Machining Department Finishing Department Manufacturing overhead costs $9,180,000 $8,181,000...
A company which uses a job-costing system, had two jobs in process at the start of...
A company which uses a job-costing system, had two jobs in process at the start of February 2018: Job no. J6 with a cost of $110,000 and job no. F1 with a cost of $22,000. The following information is available: The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,366,000 and 102,000 hours, respectively. The company worked on four jobs during February. Direct materials used, direct...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $66,000 and 22,000 hours, respectively. In June, Job #461 was completed. Materials costs on the job totaled $4,923 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked 23,975 direct...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,240,200 in manufacturing overhead cost at an activity level of 573,000 machine-hours. The company spent the entire month of January working on a large order for 8,400 custom made machined parts. The company had no...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,170,000 in manufacturing overhead cost at an activity level of 556,000 machine-hours. The company spent the entire month of January working on a large order for 8,900 custom made machined parts. The company had no...
A job-order costing system that relies on normal costing will: Multiple Choice Assign actual direct materials...
A job-order costing system that relies on normal costing will: Multiple Choice Assign actual direct materials and direct labor costs to jobs. Apply overhead cost to jobs by multiplying an actual overhead rate by the estimated amount of the allocation base incurred by the jobs. Apply overhead cost to jobs by multiplying an actual overhead rate by the actual amount of the allocation base incurred by the jobs. Apply overhead cost to jobs by multiplying a predetermined overhead rate by...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
Craigco uses job costing for its product costing. They use direct labor hours as a cost...
Craigco uses job costing for its product costing. They use direct labor hours as a cost driver. They expect overhead for the next month to be $12,000. They expect to have 550 direct labour hours over the next month. Craigco pays an average of $25.50 per labour hour. a) What is Craigco’s predetermined manufacturing overhead rate? b) Calculate the manufacturing overhead to be allocated to job #1315 that used 105 direct labour hours. c) Assuming job #1315 used $5,000 in...