Question

Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at...

Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at $25 per machine hour.

The company is considering adopting an activity-based costing system with the following data:

Activity Cost Driver Rate
Materials handling Pounds of material $1.50
Lathe work Number of parts $1.00
Milling Number of machine hours $8.00
Grinding Number of turns $0.40
Testing Number of units tested $15.00

The two jobs processed in the month of May had the following characteristics:

Job A Job B
Direct material $18,400 $60,600
Direct labor $6,000 $12,000
Pounds of material 900

3,000

Number of parts 450

1,500

Number of turns 10,000 40,000
Number of machine hours 375 800
Number of units in each job 80 200

All units tested.

Q. The difference in total cost between ABC and the volume-based costing system for Job B is:

Group of answer choices

$11,400

$20,000

$5,000

$69,600

Homework Answers

Answer #1

Answer - $11,400

Calculation:

Total Cost for Job B ads per Volume-Based Costing System =

Direct Material + Direct Labor + Overhead Cost

= 60,600 + 12,000 + (800 * 25)

= $92,600

Total Cost for Job B as per Activity Based Costing System:

Statement showing computation of Total Cost of Job B as per ABC System

Cost Driver (including figure) Rate ($) Amount ($)

Direct Material

Direct Labor

Materials Handling

Lathe Work

Milling

Grinding

Testing

-

-

Pounds of Material (3000)

Number of Parts (1500)

Number of Machine Hours (800)

Number of Turns (40000)

Number of Units Tested (200*)

-

-

1.50

1.00

8.00

0.40

15.00

60,600

12,000

4,500

1,500

6,400

16,000

3,000

Total Cost - - $104,000

* Since all units are tested, number of units tested will be equal to number of units in the job. Number of units in the job = 200 units

Difference = 104,000 - 92,600

= $11,400

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at $25 per machine hour. The company is considering adopting an activity-based costing system with the following data: Activity Cost Driver Rate Materials handling Pounds of material $1.50 Lathe work Number of parts $1.00 Milling Number of machine hours $8.00 Grinding Number of turns $0.40 Testing Number of units tested $15.00 The two jobs processed in the month of May had the following characteristics: Job...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at $25 per machine hour. The company is considering adopting an activity-based costing system with the following data: Activity Cost Driver Rate Materials handling Pounds of material $1.50 Lathe work Number of parts $1.00 Milling Number of machine hours $8.00 Grinding Number of turns $0.40 Testing Number of units tested $15.00 The two jobs processed in the month of May had the following characteristics: Job...
TG corp' s single predetermined overhead rate is $114 per direct labor hour. Under their ABC...
TG corp' s single predetermined overhead rate is $114 per direct labor hour. Under their ABC system they have 5 OH pools with the following rates: material handling $0.35 per part, lathe work $0.15 per lathe turn, milling $26 per machine hour, grinding $0.80 per part, and testing at $21 per unit tested. Based on the following information calculate the cost per unit for Job 421 using the ABC overhead system: Direct material cost per job: $10,000 (job 420), $60,000...
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead....
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead. This year, the company has budgeted to produce 1721 units of one of its products. Each unit requires 4 hours of direct labour. For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The following are the activities, budgeted total cost and cost drivers per activity for the upcoming year: Activity Cost...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production 200,000 Fixed manufacturing overhead cost $1,300,000 Variable manufacturing overhead cost per machine-hour $3.00 1.a - Compute the predetermined overhead rate – (12 points) 1. b - During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials...
4A. Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
4A. Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 80,000 Total fixed manufacturing overhead cost $ 312,000 Variable manufacturing overhead per machine-hour $ 2.10 Recently, Job T629 was completed with the following characteristics: Number of units in the job 50 Total machine-hours 200 The predetermined overhead rate is closest to: Multiple Choice $8.10 per...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 654,000 Variable manufacturing overhead cost per machine-hour $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 152,000 Fixed manufacturing overhead cost $ 654,000 Variable manufacturing overhead cost per machine-hour $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 155,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT