Question

Winterville Heating & Cooling uses job costing. Overhead is allocated to each job based on the...

Winterville Heating & Cooling uses job costing. Overhead is allocated to each job based on the number of labor hours spent on that job.  

At the beginning of the year, Winterville estimated that OH for the coming year would be $117,600. It also anticipated using 5,600 direct labor hours for the year.

What is Winterville's predetermined OH rate based on direct labor hours?

Homework Answers

Answer #1

Solution:

Predetermined Overhead Rate = Estimated Total Overhead Cost / Estimated Total units in the Allocation Base

Note:Overhead rate is calculated on the allocation base units.

Here,

Overhead is Allocated to each job on the basis of direct labor hours spent.

Therefore,here the allocation base to calculate predetermined overhead rate is Direct labour hours.

Predetermined Overhead Rate = Estimated total overhead cost / Estimated total direct labor hours

= $117,600 / 5,600 direct labor hours

= $21 per direct labor hour.

Hence, Winterville's predetermined overhead rate based on direct labour hours is $21 per direct labour hour.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $678,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 30 Total direct labor-hours 300 Direct materials $ 1,350 Direct labor cost $ 11,400...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours      30,500 Total fixed manufacturing overhead cost   $   610,000 Variable manufacturing overhead per machine-hour   $   6.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job      10 Total machine-hours      30 Direct materials   $   690 Direct labor cost   $   1,370...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,500 Total fixed manufacturing overhead cost $455,000 Variable manufacturing overhead per machine-hour $ 5.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 710 Direct labor cost $1,420 If the company marks...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct labor-hours. At the start of the year, MOH cost was estimated at $100,000 for the year. And, the number of DL hours to be used during the year was estimated at 40,000. In September, Job #274 was completed at a cost of $5,000 in direct materials and $2,400 in direct labor. The labor rate is $6 per hour. By the end of the year,...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $ 96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 755 Direct labor cost $...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,000 Total fixed manufacturing overhead cost $ 252,000 Variable manufacturing overhead per machine-hour $ 2.10 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 675 Direct labor cost $ 1,050 The estimated total...
Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 58,000 direct labor-hours, total fixed manufacturing overhead cost of $58,000, and a variable manufacturing overhead rate of $2.90 per direct labor-hour. Recently Job X387 was completed and required 220 direct labor-hours. Required: Calculate the amount of overhead applied to Job X387
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $ 96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 755 Direct labor cost $...
Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the...
Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the beginning of each year based on estimated manufacturing overhead costs and estimated direct labor-hours for the upcoming year. If the company sets its prices to cover actual direct materials costs, actual direct labor costs, and applied manufacturing overhead costs, will the company at least avoid a loss during the year?
Assume that Mason Company uses departmental predetermined overhead rates. The Machining Department is allocated based on...
Assume that Mason Company uses departmental predetermined overhead rates. The Machining Department is allocated based on machine-hours and the Assembly Department is allocated based on direct labor-hours. How much manufacturing overhead cost would be applied to Job A? Job B? Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT