A predetermined manufacturing overhead rate can be based on each of the following except direct labor hours. number of units. machine hours. direct labor costs
The Answer is “Number of Units”
- A predetermined manufacturing overhead rate can be computed based on either direct labor hours or machine hours or direct labor costs.
- A predetermined manufacturing overhead rate is the amount of indirect manufacturing cost to be charged to each unit of production.
- Predetermined Manufacturing overhead rate is a budgeted manufacturing cost per unit of activity
- The Number of Units shall not be considered in activity base for calculating the Predetermined Manufacturing Overhead rate
- Predetermined Manufacturing Overhead rate = Estimated Total Manufacturing Overhead costs / Estimated Total Amount or number of hours in the allocation base