When using a flexible budget, an increase in activity within the relevant range:
decreases fixed cost per unit.
increases variable cost per unit.
decreases total costs.
decreases total variable costs.
When using a flexible budget, an increase in activity within the relevant range decreases fixed cost per unit. |
Total fixed costs remains constant within the relevant range. When activity level increases, fixed cost per unit decreases. |
Total variable costs and total costs increases with increase in activity within the relevant range. |
Variable cost per unit remains constant within the relevant range. |
Option A decreases fixed cost per unit is correct |