At a volume of 10,000 units, Company P incurs $30,000 in factory overhead costs, including $10,000...

At a volume of 10,000 units, Company P incurs $30,000 in factory overhead costs, including $10,000 in fixed costs. Assuming that this activity is within the relevant range, if volume increases to 12,000 units, Company P would expect to incur total factory overhead costs of:

[[selectone]]

a. $34,000

b. $32,000

c. $36,000

d. $30,000

Homework Answers

Answer #1

Answer :-

P would expect to incur total factory overhead costs of : -

Total Unit Volume 10000 Units
Total Factory Overhead Costs $          30,000.00
Fixed Cost $        (10,000.00)
Variable Cost $          20,000.00
Variable Cost/ Unit $                   2.00
Projected Units 12000 Units
Variable Costs $          24,000.00
Fixed Costs $          10,000.00
Total Factory Overhead Costs $          34,000.00

Correct option is option 1st i.e. $ 34,000.00

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
At a volume of 15,000 units, Pwerson Company incurred $45,000 in factory overhead costs, including $15,000...
At a volume of 15,000 units, Pwerson Company incurred $45,000 in factory overhead costs, including $15,000 in fixed costs. If volume increases to 17,000 units and both 15,000 units and 17,000 units are within the relevant range, then the company would expect to incur total factory overhead costs of: $51,000 $47,000 $49,000 $45,000
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.71 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,000 The fixed factory overhead volume variance is a.$0 b.$909 unfavorable c.$1,136 unfavorable d.$909 favorable
#6 Schwiesow Corporation has provided the following information: Cost per Unit Cost per Period Direct materials...
#6 Schwiesow Corporation has provided the following information: Cost per Unit Cost per Period Direct materials $ 7.05 Direct labor $ 3.50 Variable manufacturing overhead $ 1.65 Fixed manufacturing overhead $ 11,000 Sales commissions $ 1.00 Variable administrative expense $ 0.40 Fixed selling and administrative expense $ 5,500 For financial reporting purposes, the total amount of period costs incurred to sell 5,000 units is closest to: $5,500 $8,300 $12,500 $7,000 #3 Kesterson Corporation has provided the following information: Cost per...
1. Which of the following costs is typically not a fixed overhead cost for a factory?...
1. Which of the following costs is typically not a fixed overhead cost for a factory? A.Salaries of factory supervisors. B.Rent on the factory building. Property taxes on the factory building. C.Indirect materials used in production. D. None of the answer choices is correct. 2.Which of the following costs does not change in total when the activity level increases or decreases within the relevant range? A.mixed costs B.fixed cost C.variable costs D.relevant costs E.None of the answer choices is correct....
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High Direct labor-hours 52,800 70,400 Total factory overhead costs $ 286,620 $ 328,860 The factory overhead costs above consist of indirect materials, rent, and...
Petra Company uses standard costs for cost control and internal reporting. Fixed costs are budgeted at...
Petra Company uses standard costs for cost control and internal reporting. Fixed costs are budgeted at $36,000 per month at a normal operating level of 10,000 units of production output. During October, actual fixed costs were $40,000, and actual production output was 12,000 units. Required a Determine the fixed overhead budget variance. b Assume that the company applied fixed overhead to production on a per-unit basis. Determine the fixed overhead volume variance. Was the fixed overhead budget variance from requirement...
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.72 per hour Variable overhead 3 hours per unit at $1.99 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $7,900 The total factory overhead cost variance is
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour Variable overhead 3 hours per unit @ $2.06 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $7,900 The fixed factory overhead volume variance is a.$720 unfavorable b.$0 c.$576 unfavorable d.$576 favorable The following data are given for Bahia Company: Budgeted...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $2.01 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $7,900 The total factory overhead cost variance is a.$-90 unfavorable b.$610 unfavorable c.$1,310 favorable d.$610 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.78 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $17,800     Total fixed cost, $8,100 The variable factory overhead controllable variance is a.$1,756 favorable b.$1,756 unfavorable c.$1,405 favorable d.$0
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT