Question

The accountant of ABC Company has the following maintenance costs and working hours for the past...

The accountant of ABC Company has the following maintenance costs and working hours for the past five months and trying to separate the cost to its components:

Month

Cost

Working hours

March

$100,000

5,000

April

60,000

1,000

May

68,600

2,000

June

83,450

3,420

July

88,000

5,250

what is the variable cost per hour?

[[selectone]]

a. $16 per hour

b. $14 per hour

c. $10 per hour

d. $12 per hour

Homework Answers

Answer #1

This question is related to High-low method. Under this method the variable cost per unit is estimated by dividing the difference of cost at highest and lowest level of activity by the difference in highest and lowest level of activity.

Cost at highest activity level = $100,000 (March)

Cost at lowest activity level = $60,000 (April)

Variable Cost per Hour = Difference in Cost at Highest and Lowest Activity Level / Difference of highest and lowest activity level

= ($100,000 – 60,000) / (5,000 – 1,000 working hours)

= $40,000 / 4,000 hours

= $10 per hour

Hence, the correct option is c. $10 per hour

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The accountant of ABC Company has the following maintenance costs and working hours for the past...
The accountant of ABC Company has the following maintenance costs and working hours for the past five months and trying to separate the cost to its components: Month Cost Working hours March $100,000 5,000 April 60,000 1,000 May 68,600 2,000 June 83,450 3,420 July 88,000 5,250 what is the predicted cost of 6,200 hours? [[selectone]] a. $124,400 b. $112,000 c. $102,000 d. $149,200
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March...
Company has presented the following information for the past eight months operations Machine-Hours Maintenance Cost March 4,440 $50,950 April 4,431 $50,877 May 4,412 $50,696 June 4,460 $51,113 July 4,414 $50,711 August 4,433 $50,900 September 4,443 $50,976 October 4,415 $50,730 November 4,391 $50,530 Management believes that maintenance cost is a mixed cost that depends on machine-hours. Using the high-low method, calculate a. Variable cost per machine-hour b.  Fixed cost per month c. What would total costs be for a month with 4,000...
Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799...
Slonaker Inc. has provided the following data concerning its maintenance costs: Machine-Hours Maintenance Cost   April 5,799           $30,379           May 5,782           $30,289           June 5,764           $30,237           July 5,761           $30,233           August 5,717           $30,078           September 5,795           $30,360           October 5,809           $30,388           November 5,801           $30,378           December 5,785           $30,318         Management believes that maintenance cost is a mixed cost that depends on machine-hours. Required: Estimate the variable cost per machine-hour and...
Rosbell Industries accountant collected the following monthly expenses data for use in analyzing the cost behaviors...
Rosbell Industries accountant collected the following monthly expenses data for use in analyzing the cost behaviors of the maintenance cost of the new machine. Month Total   MaintenanceCosts Total     MachineHours January $1,584 2,100 February $1,800 2,400 March $2,160 3,600 April $2,772 4,800 May $1,920 3,000 June $2,700 4,740 Determine the fixed and variable cost components using the high-low method.   Determine the expected Maintenance Cost for the month of July if the company expect to use the machine for 4,900 hours.
Colombia Company has provided the following data for maintenance cost: Prior Year Current Year   Machine hours...
Colombia Company has provided the following data for maintenance cost: Prior Year Current Year   Machine hours 18,000        20,300          Maintenance cost $34,700        $37,460        Maintenance cost is a mixed cost with variable and fixed components. The fixed and variable components of maintenance cost are closest to: rev: 12_20_2016_QC_CS-72978 $13,100 per year plus $.833 per machine hour $24,360 per year plus $.833 per machine hour $13,100 per year plus $1.20 per machine hour $34,700 per year plus $1.20 per...
Tecscin Company manufactures motorcycles. The company's management accountant wants to calculate the fixed and variable costs...
Tecscin Company manufactures motorcycles. The company's management accountant wants to calculate the fixed and variable costs associated with utility cost incurred by the factory. Data for the past five months were collected as follows: ​ ​ Utility Machine Month cost hours March $4,000 300 April 3,300 240 May 4,100 310 June 3,200 256 July 3,050 278 ​ Using a regression program, the value of the intercept (rounded to the nearest whole number) is calculated as: a. $1,289. b. $3,256. c....
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows:...
Machine hours and electricity costs for AMK Industries for the past eleven months were as follows: Month Electricity Costs Machine Hours January $12,600 8000 February 14,333 9600 March 9,333 5600 April 15,667 10200 May 19,167 9200 June 15,134 13200 July 16,834 14400 August 15,500 12000 September 10,667 6000 October 17,667 13200 November 21,000 16800 Required: a. Using the high-low method, develop an estimate of variable electricity costs per machine hour. b. Using the high-low method, develop an estimate of fixed...
Ken-Ken Company has determined that their maintenance cost is a mixed cost and aims to perform...
Ken-Ken Company has determined that their maintenance cost is a mixed cost and aims to perform segregation technique. They observed the maintenance cost over a six-month period according to behavior with machine hours, their main cost driver. Use high-low method and compute the following below. Month Maintenance Cost Machine Hours January 5,400.00   900.00 February 6,000.00 1,050.00 March 7,200.00 1,500.00 April 9,000.00 2,070.00 May 6,400.00 1,200.00 June 11,000.00 2,100.00 1. Variable cost rate per hour 2. Fixed cost 3. Expected total...
Compute for the missing amount. The total maintenance costs of Silver Company in the last four...
Compute for the missing amount. The total maintenance costs of Silver Company in the last four months are presented below: Month Machine hours                        Maintenance cost                 January                    7, 200                                      P450, 000                 February                  6, 800                                      P422, 000                 March                      7, 000                                      P440, 000                 April                        6, 400                                      P418, 000 Requirements: a.Variable cost per machine hour b. Total fixed cost c.Budgeted maintenance cost in May if the company is planning to use 7, 500 hours. d. Budgeted maintenance cost in May...
The following information is available for a company’s maintenance cost over the last twelve months: Month...
The following information is available for a company’s maintenance cost over the last twelve months: Month Maintenance Hours Maintenance Cost January 43 $43,820 February 38 $45,010 March 35 $44,000 April 31 $45,000 May 36 $43,200 June 28 $38,760 July 18 $32,300 August 19 $35,440 September 25 $37,500 October 29 $39,560 November 34 $42,100 December 39 $46,700 Based on the high-low method, what is the variable and fixed cost component of total maintenance cost? Variable cost per unit: $ Fixed cost:...