Question

Indiana Co. began a construction project in 2018 with a contract price of $162 million to...

Indiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018 Indiana Incurred $32 million of costs and estimates and additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Supposed that in 2019, Indiana Incurred additional costs of $63 million and estimated an additional $52 million in costs to complete the project. Indiana recognized how much on the project in 2019?

Homework Answers

Answer #1

Percentage Completion = Cost Incurred/ Estimated Total Cost : 2018 = 32/(32+85) = 27.35%

Estimated Profit = Contract Price - Estimated Total Cost : 162-117 =45

Recognize in 2018 = 45* 27.35% = 12.3075 .

2019

Percentage Completion = (32+ 63) / (32+63+52) = 64.6258 %

Estimated Profit = 162 -(32+63+52) = 15

Recognize in 2019 = 15* 64.6258% =9.6938

Since 12.3075 recognised in 2018, in 2019 2.6137 (12.3075 - 9.6938) a loss to be recognized.

(Note: 4 decimal points taken here, maybe slight variation will be there according with the decimals taken and rounded.)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $32 million of costs and estimates an additional $87 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $52 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $65 million...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to be received when the project is completed in 2023. During 2021, Georgia incurred $30 million of costs and estimates an additional $82 million of costs to complete the project. Georgia recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.    In 2022, Georgia incurred additional costs of $59 million and...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $50 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $88 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Multiple Choice: A) Recognized $36.00 million loss on the project in...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of Multiple Choice a. $900 b. $2,700 c. $0 d. $5,400 2. Mary signed up and...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m....
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project. Assuming that ESAU books $3.0m of expenses for this project in 2019, provide...
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m....
During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project. Assuming that ESAU books $3.0m of expenses for this project in 2019, provide...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...