Manning boating Co. uses a job order cost system. Each customer’s house is treated as a separate job. Overhead is applied to each job based on number of roofing hours required for the job. Data is as follows:

Estimated overhead           $800,000

Actual overhead                  $772,450

Actual roofing hours              36,700

Estimated roofing hours        40,000

a. Compute the predetermined overhead rate

b. Prepare the entry to apply overhead for the year

c. Determine whether overhead is over or underapplied, and by how much. Use a T account to show your work.

d. Prepare the journal entry need to close out MOH

Homework Answers

Answer #1

The answer has been presented in the supporting sheet.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Tombert Decorating uses a job order cost system to collect the costs of its interior decorating...
Tombert Decorating uses a job order cost system to collect the costs of its interior decorating business. Each client’s consultation is treated as a separate job. Overhead is applied to each job based on the number of decorator hours incurred. Listed below are data for the current year. Estimated overhead $1,040,000 Actual overhead $1,040,800 Estimated decorator hours 40,000 Actual decorator hours 39,600 The company uses the account Operating Overhead in place of Manufacturing Overhead and the account Service Contracts in...
Baxter Corp uses a normal job order costing system with manufacturing overhead applied to products on...
Baxter Corp uses a normal job order costing system with manufacturing overhead applied to products on the basis of direct labor hours. For the upcoming year, Baxter Corp estimated total manufacturing overhead cost at $480,000 and total direct labor hours of 40,000. During the year actual manufacturing overhead incurred was $462,500 and 41,000 direct labor hours were used. a. Calculate the predetermined overhead rate. b. Calculate how much manufacturing overhead will be applied to production. c. Is overhead over- or...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.80 per machine-hour was based on a cost formula that estimates $232,400 of total manufacturing overhead for an estimated activity level of 83,000 machine-hours. Required: 1. Assume that during the year the company works only 78,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Luzadis Company makes furniture using the latest automated technology. The company uses a job-order costing system...
Luzadis Company makes furniture using the latest automated technology. The company uses a job-order costing system and applies manufacturing overhead cost to products on the basis of machine-hours. The predetermined overhead rate was based on a cost formula that estimates $735,000 of total manufacturing overhead for an estimated activity level of 49,000 machine-hours. During the year, a large quantity of furniture on the market resulted in cutting back production and a buildup of furniture in the company’s warehouse. The company’s...
Granite Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a...
Granite Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year, manufacturing overhead and direct labor-hours were estimated at $80,000 and 16,000 hours respectively, for the year. In June, Job #315 was completed. Materials costs on the job totaled $1,500 and labor costs totaled $2,400 at $6 per hour. At the end of the year, it was determined that the company worked 15,000 direct labor-hours for...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $135,000 for the year and the estimated direct labor hours were 15,000 hours. In May, Job #378 was completed. Direct materials totaled $8,500. Total labor costs were $14,000 at $16 per hour. At the end of the year, it was determined that the company worked 16,000 direct labor...
Job Order Costing Data Allocation base Machine-hours Estimated manufacturing overhead cost $300,000 Estimated total amount of...
Job Order Costing Data Allocation base Machine-hours Estimated manufacturing overhead cost $300,000 Estimated total amount of the allocation base 75,000 machine-hours Actual manufacturing overhead cost $290,000 Actual total amount of the allocation base 68,000 machine-hours Enter a formula into each of the cells marked with a ? below Computation of the predetermined overhead rate Estimated manufacturing overhead cost ? Estimated total amount of the allocation base ? machine-hours Predetermined overhead rate ? per machine-hour Computation of underapplied or overapplied manufacturing...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct labor-hours. At the start of the year, MOH cost was estimated at $100,000 for the year. And, the number of DL hours to be used during the year was estimated at 40,000. In September, Job #274 was completed at a cost of $5,000 in direct materials and $2,400 in direct labor. The labor rate is $6 per hour. By the end of the year,...
The York Co. uses a job order cost system and applies factory overhead to individual jobs...
The York Co. uses a job order cost system and applies factory overhead to individual jobs by using predetermined overhead rates. In department X, overhead is applied on the basis of machine hours, and in department Y, on the basis of direct labor hours. At the beginning of the current year, management made the following budget estimates: Dept X Dept Y Direct Labor $210,000 $384,000 Factory Overhead $216,000 $105,000 Machine Hours 36,000 900 Direct Labor Hours 18,000 25,000 Production order...
The York Co. uses a job order cost system and applies factory overhead to individual jobs...
The York Co. uses a job order cost system and applies factory overhead to individual jobs by using predetermined overhead rates. In department X, overhead is applied on the basis of machine hours, and in department Y, on the basis of direct labor hours. At the beginning of the current year, management made the following budget estimates: Dept X Dept Y Direct Labor $210,000 $384,000 Factory Overhead $216,000 $105,000 Machine Hours 36,000 900 Direct Labor Hours 18,000 25,000 Production order...