Question

How the capacity level chosen to compute the budgeted fixed overhead cost rate affect the production-volume...

How the capacity level chosen to compute the budgeted fixed overhead cost rate affect the production-volume variance?

Homework Answers

Answer #1

Solution:

The formula for Production volume variance

= (Actual units produced – Budgeted production units) X Budgeted Overhead Rate per unit


So, as per the above formula, Production volume Variance is actually the difference of Actual and Budgeted production multiplied by Budgeted Overhead rate per unit.
Thus, Budget fixed overhead cost rate is an affecting factor in the variance. And Budgeted production is considered as per the capacity level chosen.

So, ultimately the capacity level chosen to compute the budgeted fixed overhead cost rate affect the production volume variance.


PLEASE LIKE THE ANSWER IF YOU FIND IT HELPFUL OR YOU CAN COMMENT IF YOU NEED CLARITY / EXPLANATION ON ANY POINT.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
True-False ____1. Budgeted overhead cost rates can be expressed as an amount per unit of output...
True-False ____1. Budgeted overhead cost rates can be expressed as an amount per unit of output or per unit of input. ____2. There is no fundamental difference between the budgeted variable-overhead cost rate per unit of input and the budgeted price of individual direct materials. ____3. The variable-overhead spending variance is unfavorable if the actual variable overhead cost rate per unit of input (the cost-allocation base) is greater than the budgeted variable overhead cost rate per unit of input. ____4....
Lihue, Inc., applies fixed overhead at the rate of $4.00 per unit. Budgeted fixed overhead was...
Lihue, Inc., applies fixed overhead at the rate of $4.00 per unit. Budgeted fixed overhead was $1,393,200. This month 342,300 units were produced, and actual overhead was $1,380,000. Required: What are the fixed overhead price and production volume variances for Lihue? fixed overhead price variance fixed overhead production volume variance b. What was budgeted production for the month?
Lihue, Inc., applies fixed overhead at the rate of $4.20 per unit. Budgeted fixed overhead was...
Lihue, Inc., applies fixed overhead at the rate of $4.20 per unit. Budgeted fixed overhead was $1,457,820. This month 342,100 units were produced, and actual overhead was $1,450,000. Required A What are the fixed overhead price and production volume variances for Lihue? (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.) Fixed overhead price variance    Fixed overhead production volume variance Required B: What...
1.a fixed overhead rate based on_______ highlights for management attention the cost of unutilized capacity. a....
1.a fixed overhead rate based on_______ highlights for management attention the cost of unutilized capacity. a. budgeted production b practical capacity c utilized capacity d. actual production 2. the formula AQ x (SP - AP) is the: a. direct materials spending variance b. direct materials volume variance c. direct materials price variance d. direct materials quantity variance 3. the formula SP x (SQ - AQ) is the: a. direct materials spending variance b. direct materials volume variance c. direct materials...
The difference between budgeted fixed manufacturing overhead and the fixed overhead applied to production is the:...
The difference between budgeted fixed manufacturing overhead and the fixed overhead applied to production is the: Select one: a. sum of the spending and efficiency variances. b. efficiency variance. c. spending variance. d. volume variance. e. controllable variance.
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable factory overhead $97,000 Fixed factory overhead 32,000 Standard: 5,000 hrs. at $24 120,000 If productive capacity of 100% was 8,000 hours and the total factory overhead cost budgeted at the level of 5,000 standard hours was $132,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $190,100 Fixed factory overhead 45,500 Standard: 8,000 hrs. at $28 224,000 If productive capacity of 100% was 13,000 hours and the factory overhead cost budgeted at the level of 8,000 standard hours was $241,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $98,500 Fixed factory overhead 38,500 Standard: 7,000 hrs. at $18 126,000 If productive capacity of 100% was 11,000 hours and the factory overhead cost budgeted at the level of 7,000 standard hours was $140,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $90,200 Fixed factory overhead 34,500 Standard: 4,000 hrs. at $29 116,000 If productive capacity of 100% was 6,000 hours and the total factory overhead cost budgeted at the level of 4,000 standard hours was $127,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $116,400 Fixed factory overhead 30,000 Standard: 4,000 hrs. at $35 140,000 If productive capacity of 100% was 6,000 hours and the factory overhead cost budgeted at the level of 4,000 standard hours was $150,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...