Question

Multiple Choice Question 81 Sheffield Corp. planned to use 1 yard of plastic per unit budgeted...

Multiple Choice Question 81

Sheffield Corp. planned to use 1 yard of plastic per unit budgeted at $106 a yard. However, the plastic actually cost $105 per yard. The company actually made 5100 units, although it had planned to make only 4300 units. Total yards used for production were 5160. How much is the total materials variance?
$8480 U
$1200 U
$5160 F
$84800 U
Click if you would like to Show Work for this question:

Open Show Work

Question Attempts: 0 of 1 used

SAVE FOR LATER

SUBMIT ANSWER

Homework Answers

Answer #1

Ans. Option B $1,200 U

*Working Notes:

*Calculation of total standard cost:

Total standard cost = Standard quantity per unit * Actual production * Standard price

= 1 * 5,100 * $106

= $540,600

*Calculation of total actual cost :

Total actual cost = Actual quantity used * Actual price

= 5,160 * $105

= $541,800

*Calculation of total materials variance:

Total materials variance = Total standard cost - Total actual cost

= $540,600 - $541,800

= -$1,200 (or $1,200 unfavorable)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT