Top Hand company makes a tote bag and uses a standard cost system. Each tote bag should use 2 yards of material that costs $5.00 per yard. Stitching on each bag should take a half hour of labor time of line workers who are paid an average wage of $20 per hour. Last month 15,000 tote bags were produced.
Looking at the production records, you find that $144,000 was spent to purchase the 32,000 yards of material used in production. Stitchers worked 7,200 hours and were paid $158,400.
You have been asked to produce a production report.
Required: Be sure to label each variance as F – favorable or U – unfavorable.
1. What is the standard materials costs for a tote bag and what is the standard labor cost to produce a tote bag?
2. What were the total direct materials and direct labor variances?
3. Calculate the following variance breakdowns for last month’s production:
Materials price variance
Materials usage variance
Labor price (rate) variance
Labor usage (efficiency) variance
Get Answers For Free
Most questions answered within 1 hours.