Question

The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...

The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory 1,000 units (100% complete as to materials and 50% complete as to labor and overhead); Units started in production 19,000; Units finished during the period 16,000; Units in process at the end of the period (100% complete as to materials and 25% complete as to labor and overhead) 4,000; Costs in beginning inventory were materials of $1,500 and Labor and overhead costs $1,000; Cost added during the period were $35,200 for materials and Labor and overhead costs of $37,400.

What is the weighted average value of materials transferred out of ending Work in Process Inventory for the period? (Round to the nearest $1.00.)

Homework Answers

Answer #1

Equivalent unit of production for materials- (weighted average method)

Completed units - 16000

Ending inventory - 4000

EUP - 20000

Total material cost-

In weighted average method, both the material cost of beginning inventory and material cost added during the period are taken to allocate to products.

Therefore material cost = 1500 + 35200

= 36700.

Material cost per unit = Total material cost / EUP

= 36700 / 20000

= 1.84

Material cost for completed units = 16000 * 1.84

=$ 29440//

Material cost for ending inventory = 4000 * 1.84

=$ 7360//

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 24,000 Units finished during the period 17,900 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 6,100 Cost of materials used $ 60,500 Labor and overhead costs $ 62,480 Total cost of the 17,900 units finished is: $102,698. $111,447. $123,011. $109,467.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 22,600 Units finished during the period 17,200 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,400 Cost of materials used $ 51,120 Labor and overhead costs $ 39,165 Total cost of the 17,200 units finished is: (Round intermediate calculations to two decimal places and round your final...
Hershey Chocolate Company uses a weighted-average process costing system. Hershey provides the following data:   Beginning inventory...
Hershey Chocolate Company uses a weighted-average process costing system. Hershey provides the following data:   Beginning inventory -0-     Units started in production 35,400     Units finished during the period 30,000     Units in process at the end of the period   (Complete as to materials, 1/4 complete as to labor and overhead) 5,400     Cost of materials used $ 61,200     Labor and overhead costs $ 112,860   Equivalent units of production for labor and overhead are: 30,000. 35,400. 31,350. 32,700. Some other amount.
A firm that uses weighted average process costing has the following data: Beginning Inventory (2,000 physical...
A firm that uses weighted average process costing has the following data: Beginning Inventory (2,000 physical units): Direct Materials: $2,500 100% complete Conversion: $4,000 80% complete Ending Inventory (8,000 physical units): Direct Materials: 100% complete Conversion: 0% complete Current Costs: Direct Materials: $45,500 Conversion: $76,000 Units started during the period 46,000 Units completed and transferred to finished goods 40,000 Required: Calculate the cost per unit for direct materials and conversion costs. DIRECT MATERIALS (5 pts.): ___________________ CONVERSION COSTS (5 pts):
CallahanCallahan Company uses the? weighted-average method in its process costing system. The Packaging Department started the...
CallahanCallahan Company uses the? weighted-average method in its process costing system. The Packaging Department started the month with 290290 units in process that were 8080?% ?complete, received 1 comma 4901,490 units from the Finishing? Department, and had 140140 units in process at the end of the period. All materials are added at the beginning of the? process, and conversion costs are incurred uniformly. The units in process at the end of the month are 1010?% complete with respect to conversion...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 1,000 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 6,300 65% Conversion costs $ 7,400 45% A total of 7,700 units were started and 6,500 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Gunes Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Gunes Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 10,600 65% Conversion costs $ 12,800 30% A total of 8,500 units were started and 7,400 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Esty Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Esty Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 800 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 5,800 50% Conversion costs $ 6,500 30% A total of 7,700 units were started and 6,600 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 2,300 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 7,600 65% Conversion costs $ 8,700 45% A total of 10,300 units were started and 7,800 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Camino Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory...
Camino Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 400 units. The costs and percentage completion of these units in beginning inventory were: Percent Complete Materials costs $      5,628 50% Conversion costs $      4,155 20% A total of 6,800 units were started and 6,100 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department during...