MCE
Craig, Inc., has provided the following information for one of its products for each hour of production:
Actual velocity: 100 units (per hour) |
Move time: 13 minutes |
Inspection time: 10 minutes |
Rework time: 13 minutes |
Required:
1. Calculate MCE. If required, round your answer to two decimal places.
2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places.
Theoretical cycle time | minutes | |
Actual cycle time | minutes | |
MCE |
3. What if waste is
reduced by 45 percent?
New waste = minutes
What is the new MCE? If required, round your answer to two decimal places.
What is the new cycle time?
minutes
1. Ans :, Manufacturing cycle efficiency(MCE)
=Value added time /Non value added time
Value added time=process time
=total time - non value added time
=60 -(13+10+13)
=60-36
=24 min
MCE=24/60=0.4
2.ans
Theoretical cycle time
= Process time per unit of production
= 24/100
=0.24 minutes
Actual cycle time
= total time per unit of production
= 60/100
=0.6 minutes
MCE using theoretical cycle and actual times
= theoretical cycle time/actual cycle time
=0.24/0.6
= 0.4
3. New waste
= (total time-process time) x useful time%
= (60 - 24) x 55%. (100-45%=55%)
= 19.8 minutes