Question

Problem 15.21 LO 4, 5 Direct labor variances - insurance company application The Foster Insurance Company...

Problem 15.21 LO 4, 5

Direct labor variances - insurance company application The Foster Insurance Company developed standard times for processing claims. When a claim was received at the processing center, it was first reviewed and classified as simple or complex. The standard time for processing was:

Simple claim......................................................36 minutes

Complex claim...................................................1.25 hours

Employees were expected to be productive 7.5 hours per day. Compensation costs were $135 per day per employee. During July, which had 20 working days, the following number of claims were processed:

Simple claims....................................................3,000 processed

Complex claims..................................................960 processed

Required:

a. Calculate the number of workers that should have been available to process July claims.

b. Assume that 23 workers were actually available throughout the month of July. Calculate a labor efficiency variance expressed as both a number of workers and a dollar amount for the month.

Homework Answers

Answer #1

Answers:

a.)

Standard time for processing simple claim = 36 minutes

Standard time for processing complex claim= 1.25 hours

Expected work hours a day = 7.5 hours

Compensation cost per employee = $135 per day

Total days of work = 20

Number of process July simple claims = 3000

Number of July complex claims =960

Standard number of workers essential for the month 12 simple and 8 complex so that would give a total of 20 essential workers that are supposed to have been available to process the July claims.

.

b.)

Labor efficiency variance for July in terms of the number of workers is Calculated as follows:

= ( Actual - standard)

= 23 - 20 = 3Unfavorable

Labor efficiency variance for July in dollars = Number of workers × number of days × Pay per day

= 3 Employees × 20 Days × $135

= $8,100 Unfavaorable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Foster Insurance company developed standard times for processing claims. When a claim was received at...
The Foster Insurance company developed standard times for processing claims. When a claim was received at the processing center, it was first reviewed and classified as simple or complex. The standard time for processing was: Simple claim 60 minutes Complex claim 3.5 hours Employees were expected to be productive 8 hours per day. Compensation costs were $93 per day per employee. During April, which had 21 working days, the following number of claims were processed: Simple claims 3,100 processed Complex...
E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted...
E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted silver charms that attach to jewelry such as a necklace or bracelet. Each charm is adorned with two crystals of various colors. Standard costs follow: Standard Quantity Standard (Rate) Standard Unit Cost Silver 0.30 oz. $ 30.00 per oz. $ 9.00 Crystals 5.00 $ 0.45 per crystal 2.25 Direct labor 1.50 hrs. $ 19.00 per hr. 28.50 During the month of January, Crystal Charm...
E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted...
E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted silver charms that attach to jewelry such as a necklace or bracelet. Each charm is adorned with two crystals of various colors. Standard costs follow: Standard Quantity Standard (Rate) Standard Unit Cost Silver 0.25 oz. $ 26.00 per oz. $ 6.50 Crystals 6.00 $ 0.25 per crystal 1.50 Direct labor 1.50 hrs. $ 16.00 per hr. 24.00 During the month of January, Crystal Charm...
E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted...
E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted silver charms that attach to jewelry such as a necklace or bracelet. Each charm is adorned with two crystals of various colors. Standard costs follow: Standard Quantity Standard (Rate) Standard Unit Cost Silver 0.25 oz. $ 29.00 per oz. $ 7.25 Crystals 4.00 $ 0.40 per crystal 1.60 Direct labor 2.00 hrs. $ 18.00 per hr. 36.00 During the month of January, Crystal Charm...
3. E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes...
3. E9-5 Calculating Direct Materials and Direct Labor Variances [LO 9-3, 9-4] Crystal Charm Company makes handcrafted silver charms that attach to jewelry such as a necklace or bracelet. Each charm is adorned with two crystals of various colors. Standard costs follow: Standard Quantity Standard (Rate) Standard Unit Cost Silver 0.50 oz. $ 22.00 per oz. $ 11.00 Crystals 2.00 $ 0.35 per crystal 0.70 Direct labor 1.50 hrs. $ 12.00 per hr. 18.00 During the month of January, Crystal...
6-20 Direct labor variance calculation and explanation (LO 4, 5) Hunter Family Instruments makes cellos. During...
6-20 Direct labor variance calculation and explanation (LO 4, 5) Hunter Family Instruments makes cellos. During the past year, the company made 6,400 cellos even though the budget planned for only 5,600. The company paid its workers an average of $15 per hour, which was $1 higher than the standard labor rate. The production manager budgets four direct labor hours per cello. During the year, a total of 24,320 direct labor hours were worked. Required a.Calculate the direct labor rate...
Exercise 23-20 Computation of volume and controllable overhead variances LO P3 World Company expects to operate...
Exercise 23-20 Computation of volume and controllable overhead variances LO P3 World Company expects to operate at 80% of its productive capacity of 50,000 units per month. At this planned level, the company expects to use 25,000 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.625 direct labor hours per unit. At the 80% capacity level, the total budgeted cost includes $50,000 fixed overhead cost and $275,000 variable overhead cost. In the...
Direct Labor Variances Bellingham Company produces a product that requires 5 standard direct labor hours per...
Direct Labor Variances Bellingham Company produces a product that requires 5 standard direct labor hours per unit at a standard hourly rate of $17.00 per hour. If 5,300 units used 25,700 hours at an hourly rate of $17.68 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...
6. PA9-1 Calculating Direct Material, Direct Labor, Variable Overhead Variances [LO 9-3, 9-4, 9-5] Barley Hopp,...
6. PA9-1 Calculating Direct Material, Direct Labor, Variable Overhead Variances [LO 9-3, 9-4, 9-5] Barley Hopp, Inc., manufactures custom-ordered commemorative beer steins. Its standard cost information follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (clay) 1.80 lbs. $ 1.90 per lb. $ 3.42 Direct labor 1.80 hrs. $ 11.00 per hr. 19.80 Variable manufacturing overhead (based on direct labor hours) 1.80 hrs. $ 1.10 per hr. 1.98 Fixed manufacturing overhead ($396,000.00 ÷ 180,000.00 units) 2.20 Barley Hopp...
Direct labor variances Bellingham Company produces a product that requires 4 standard direct labor hours per...
Direct labor variances Bellingham Company produces a product that requires 4 standard direct labor hours per unit at a standard hourly rate of $20.00 per hour. 15,000 units used 62,400 hours at an hourly rate of $19.55 per hour. This information has been collected in the Microsoft Excel Online file. Open the spreadsheet, perform the required analysis, and input your answers in the questions below. Open spreadsheet What is the direct labor (a) rate variance, (b) time variance, and (c)...