1)
A professional audit firm charged juniors at $60 per hour, seniors at $200 per hour and the overhead rate for both was 150 per cent on direct labour. The firm added 10 per cent on total cost to arrive at a fee to be charged. If a job took 7 junior hours and 3 senior hours, what was the fee charged?
Select one:
a. 2345
b. 2635
c. 2805
d. 3450
2)
Softcloth Textile Pty Ltd. manufactures a variety of fabrics. The weaving department had 3,000 units in work in process on April 1 which were 20% complete as to conversion costs. During April, 15,000 units were completed and transferred. On April 30th, 6,000 units remained in work in process 40% complete as to conversion costs. Using the weighted average process costing approach, calculate the equivalent units of conversion costs as at the end of April.
Select one:
a. 14,400
b. 13,800
c. 16,800
d. 21,000
e. 17,400
3)
Seatrail Company uses the weighted-average method in its process costing system. The beginning work in process inventory in a particular department consisted of 10,000 units, 100% complete with respect to materials cost and 30% complete with respect to conversion costs. The total cost in the beginning work in process inventory was $37,600. A total of 15,000 units were transferred out of the department during the month. The costs per equivalent unit were computed to be $1.50 for materials and $3.20 for conversion costs. The total cost of the units completed and transferred out of the department was:
Select one:
a. 70500
b. 37600
c. 74260
d. 40500
1 | ||
Total direct labor cost | 1020 | =(7*60)+(3*200) |
Add: Overhead | 1530 | =1020*150% |
Total cost | 2550 | |
Add: Markup | 255 | =2550*10% |
Fee charged | 2805 | |
Option C 2805 is correct | ||
2 | ||
Units completed and transferred | 15000 | |
Add: Ending work in process | 2400 | =6000*40% |
Equivalent units of conversion costs | 17400 | |
Option E 17,400 is correct | ||
3 | ||
Units completed and transferred out | 15000 | |
X Costs per equivalent unit | 4.70 | =1.50+3.20 |
Total cost of the units completed and transferred out | 70500 | |
Option A 70500 is correct |
Get Answers For Free
Most questions answered within 1 hours.