Question

Consider the following results for one month:                                   &nbs

Consider the following results for one month:

                                                Actual              Standard overhead applied    Total variance

Machine hours                        3,000                 3,100                                                                         

Variable overhead                  $4,200               3,100 @ $1.20 = $3,720        $480 U

Fixed overhead                      $4,300               3100 @ $1.20 = $3,720         $580 U

Required:

  1. Calculate the efficiency and spending variances for variable overhead.
  2. Calculate budget and volume variances for fixed overhead costs (normal hours for the month are 3,500)

Homework Answers

Answer #1

A.

Actual Hours =3,000

Actual Varible Overhead Rate = $1.4 per labour hour ($4,200/3000)

Standard Hour = 3,100

Standard Varible Overhead Rate = $1.2

Variable Overhead Spending Variance = Actual Hours ( Standard VOH Rate- Actual VOH rate)

= 3000($1.2 -$1.4) = 3000*$0.2 = $600 Unfavourable

Variable Overhead Efficiency Variance = Standard Variable Overhead Rate(Standard Hour-Actual Hour)

= $1.2 (3,100-3,000) = $1.2*100 = $120 Favourable

B. Actual Fixed Overhead Rate = $1.433 ($4,300/3,000)

Fixed Overhead Expenditure Variance= Budgeted Fixed Overhead Cost - Actual Fixed Overhead Cost

= 3,500 Hour*$1.2 - $4,300 = $100 Unfavourable

Fixed Overhead Volume Variance = Standard Fixed Overhead Rate(Standard Hour - Budgeted Hour)

= $1.2 (3,100- 3,500) = $1.2*400 = $480 Unfavourable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,100 engines. The...
Bondi Corporation makes automotive engines. For the most recent month, budgeted production was 3,100 engines. The standard power cost is $2.20 per machine-hour. The company's standards indicate that each engine requires 10.9 machine-hours. Actual production was 3,400 engines. Actual machine-hours were 35,130 machine-hours. Actual power cost totaled $81,975. Required: Determine the rate and efficiency variances for the variable overhead item power cost and indicate whether those variances are unfavorable or favorable. (Input all amounts as positive values.) Variable overhead rate...
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine       &n
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine         Machine-Hours   Overhead Costs            hour)  8,000    9,000    10,000 Variable costs   $1.05  $ 8,400 $ 9,450 $10,500 Fixed costs       24,800   24,800   24,800 Total Overhead Costs    $33,200 $34,250 $35,300 The following information is available for a recent period: a. The denominator activity of 8,000 machine-hours was chosen to compute the predetermined overhead rate. b. At the 8,000 standard machine-hours level of activity, the company should produce 3,200 units of product. c....
**PLEASE SHOW ALL WORK / EQUATIONS NECESSARY to arrive at solutions** Crystal Glassware Company has the...
**PLEASE SHOW ALL WORK / EQUATIONS NECESSARY to arrive at solutions** Crystal Glassware Company has the following standards and flexible-budget data.       Standard variable-overhead rate $ 19 per direct-labor hour Standard quantity of direct labor 2.0 hours per unit of output Budgeted fixed overhead $ 400,000 Budgeted output 30,000 units    Actual results for April are as follows:       Actual output 19,000 units Actual variable overhead $ 1,025,150 Actual fixed overhead $ 341,000 Actual direct labor 50,500 hours...
WWW Company’s flexible budget for manufacturing overhead follows: Account Machine Hours Machine Hours Machine Hours 8,000...
WWW Company’s flexible budget for manufacturing overhead follows: Account Machine Hours Machine Hours Machine Hours 8,000 9,000 10,000 Variable Overhead $10,000 $11,250 $12,500 Fixed Overhead $28,000 $28,000 $28,000 Total Overhead Costs $38,000 $39,250 $40,500             The following additional information is available for the most recent period: The activity level of 8,000 machine hours was chosen to compute the predetermined overhead rate At 8,000 machine hours level of activity the company should produce 3,200 units of output The company’s actual operating...
Problem: The following selected information was extracted from the accounting records of Austin, Inc.: Planned manufacturing...
Problem: The following selected information was extracted from the accounting records of Austin, Inc.: Planned manufacturing activity: 40,000 machine hours Standard variable-overhead rate per machine hour: $16 Budgeted fixed overhead: $100,000 Variable-overhead spending variance: $92,000 U Variable-overhead efficiency variance: $102,000 F Fixed-overhead budget variance: $25,000 U Total actual overhead: $675,000 Actual fixed overhead: $125,000 Fixed Actual variable overhead: $550,000 Variable Actual machine hours worked: 28,625 Standard machine hours allowed: 35,000 Need to find Fixed-overhead volume variance I already know the...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following...
Question 4: Eric Co. uses machine hours to apply standard overhead cost to production. The following data pertain to October: Master budget data: Units 2,500 Total machine hours (denominator volume) 100,000 Total variable overhead cost $ 250,000 Total fixed overhead cost $ 50,000 Actual operating results: Variable overhead cost incurred $ 265,000 Fixed overhead cost incurred $ 54,000 Units manufactured 2,250 Total machine hours 96,000 Required: Compute the following variances using machine hours as the activity variable used to assign...
BLC has the following information with respect to variable manufacturing overhead for the month of June....
BLC has the following information with respect to variable manufacturing overhead for the month of June. The budget calls for 10,000 units to be produced using a total of 15,000 machine-hours. The variable overhead costs for the period are budgeted to be $180,000. During June, the actual output was 9,000 units. The total variable overhead costs were $171,000, and 14,000 machine-hours were actually used. BLC uses machine-hours to drive variable overhead. What is the variable overhead spending variance for the...
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow:   Budgeted fixed factory overhead:      Setup   $ 57,600         Other 265,000 $ 322,600   Total factory overhead incurred $ 494,000   Variable factory overhead rate:      Per setup $ 650      Per machine hour $ 4   Total standard machine hours allowed for the units manufactured 24,000 hours   Machine hours actually worked 28,000 hours...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...
Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 125,000 units requiring 500,000 direct labor hours. (Practical capacity is 520,000 hours.) Annual budgeted overhead costs total $830,000, of which $585,000 is fixed overhead. A total of 119,100 units using 498,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,100, and...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported...
GreatGreat Fender allocates manufacturing overhead to production based on standard direct labor hours. GreatGreat Fender reported the following actual results for 2016​: actual number of fenders​ produced ,20,000​; actual variable​ overhead,$5,300​; actual fixed​ overhead,$27,000​; actual direct labor​ hours,370. Read the requirements . Requirement 1. Compute the overhead variances for the​ year: variable overhead cost​ variance, variable overhead efficiency​ variance, fixed overhead cost​ variance, and fixed overhead volume variance. Begin with the variable overhead cost and efficiency variances. Select the required​...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT