Question

Exercise 10-3 Measures of Internal Business Process Performance [LO10-3] Management of Mittel Rhein AG of Köln,...

Exercise 10-3 Measures of Internal Business Process Performance [LO10-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.2 days Wait time (from order to start of production) 17.1 days Process time 3.2 days Move time 0.9 days Queue time 3.9 days

Required:

1. Compute the throughput time. (Round your answer to 1 decimal place.)

2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.)

3. What percentage of the throughput time was spent in non–value-added activities? (Round your percentage answer to nearest whole percent.)

4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)

5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Round your percentage answer to 1 decimal place.)

Homework Answers

Answer #1
1
Inspection time 0.2
Process time 3.2
Move time 0.9
Queue time 3.9
Throughput time 8.2 days
2
Process time 3.2
Divide by Throughput time 8.2
Manufacturing cycle efficiency (MCE) 39%
3
Non-value-added throughput time 61% =1-39%
4
Throughput time 8.2
Wait time 17.1
Delivery cycle time 25.3 days
5
New Manufacturing cycle efficiency 74.4% =3.2/(0.2+3.2+0.9)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln,...
Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 15.9 days Process time 2.9 days Move time 0.8 days Queue time 3.9 days Required:...
Exercise 12-3 Measures of Internal Business Process Performance [LO12-3] Management of Mittel Rhein AG of Köln,...
Exercise 12-3 Measures of Internal Business Process Performance [LO12-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 day Wait time (from order tostart of production) 16.4 days Process time 3.2 days Move time 0.5 day Queue time 3.9 days Required: 1.Compute...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 14.0 days Process time 2.7 days Move time 1.0 days Queue time 5.0 days Required: 1. Compute the throughput time. 2. Compute the manufacturing...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:   Inspection time 0.4 days   Wait time (from order to start of production) 17.0 days   Process time 3.1 days   Move time 1.1 days   Queue time 4.2 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.2 days Wait time (from order to start of production) 15.4 days Process time 3.3 days Move time 1.3 days Queue time 4.1 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.8 days Wait time (from order to start of production) 15.3 days Process time 3.3 days Move time 1.5 days Queue time 4.4 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 16.2 days Process time 3.2 days Move time 1.5 days Queue time 4.0 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.7 days Wait time (from order to start of production) 15.7 days Process time 2.9 days Move time 0.8 days Queue time 3.6 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.7 days Process time 3.0 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 15.9 days Process time 2.7 days Move time 1.2 days Queue time 3.5 days Required: 1. Compute the throughput time. (Round your answer to...