Schwann Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted...

Schwann Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted by consumers, and the company has enough orders to keep the factory production at 10,000 helmets per month (80% of its full capacity). Schwann’s monthly manufacturing cost and other expense data are as follows.

Rent on factory equipment $11,500
Insurance on factory building 1,700
Raw materials (plastics, polystyrene, etc.) 77,100
Utility costs for factory 900
Supplies for general office 400
Wages for assembly line workers 59,700
Depreciation on office equipment 900
Miscellaneous materials (glue, thread, etc.) 1,500
Factory manager’s salary 6,400
Property taxes on factory building 500
Advertising for helmets 14,500
Sales commissions 10,900
Depreciation on factory building 1,700

Enter each cost item on your answer sheet, placing the dollar amount under the appropriate headings. Total the dollar amounts in each of the columns.

Product Costs


Cost Item

Direct
Materials

Direct
Labor

Manufacturing
Overhead

Period
Costs

Rent on factory equipment

$enter a dollar amount

$enter a dollar amount

$enter a dollar amount

$enter a dollar amount

Insurance on factory building

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Raw materials

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Utility costs for factory

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Supplies for general office

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Wages for assembly line workers

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Depreciation on office equipment

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Miscellaneous materials

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Factory manager’s salary

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Property taxes on factory building

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Advertising for helmets

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Sales commissions

enter a dollar amount

enter a dollar amount

enter a dollar amount

enter a dollar amount

Depreciation on factory building

enter a dollar amount enter a dollar amount enter a dollar amount enter a dollar amount

$enter a total amount

$enter a total amount

$enter a total amount

$enter a total amount

Homework Answers

Answer #1
Cost item Direct Direct Manufacturing Period
Materials Labor overhead costs
Rent on factory equipment 11,500
Insurance on factory building 1,700
Raw materials 77,100
Utility costs for factory 900
Supplies for general office 400
Wages for assembly line workers 59,700
Depreciation on office equipment 900
Miscellaneous materials 1,500
Factory manager's salary 6,400
Property taxes on factory building 500
Advertising for helmets 14,500
Sales commissions 10,900
Depreciation on factory building 1,700
77100 59700 24,200 26700
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted by consumers, and the company has enough orders to keep the factory production at 10,000 helmets per month (80% of its full capacity). Ohno’s monthly manufacturing cost and other expense data are as follows. Rent on factory equipment $11,800 Insurance on factory building 2,100 Raw materials (plastics, polystyrene, etc.) 84,100 Utility costs for factory 1,000 Supplies for general office 400 Wages for assembly line...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted by consumers, and the company has enough orders to keep the factory production at 10,000 helmets per month (80% of its full capacity). Ohno’s monthly manufacturing cost and other expense data are as follows. Rent on factory equipment $11,800 Insurance on factory building 2,400 Raw materials (plastics, polystyrene, etc.) 79,400 Utility costs for factory 1,000 Supplies for general office 400 Wages for assembly line...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted by consumers, and the company has enough orders to keep the factory production at 10,000 helmets per month (80% of its full capacity). Ohno’s monthly manufacturing cost and other expense data are as follows. Rent on factory equipment $11,400 Insurance on factory building 2,400 Raw materials (plastics, polystyrene, etc.) 78,000 Utility costs for factory 900 Supplies for general office 400 Wages for assembly line...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted...
Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted by consumers, and the company has enough orders to keep the factory production at 10,000 helmets per month (80% of its full capacity). Ohno’s monthly manufacturing cost and other expense data are as follows. Rent on factory equipment $12,100 Insurance on factory building 2,540 Raw materials (plastics, polystyrene, etc.) 80,300 Utility costs for factory 950 Supplies for general office 310 Wages for assembly line...
Problem 19-1A Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is...
Problem 19-1A Ohno Company specializes in manufacturing a unique model of bicycle helmet. The model is well accepted by consumers, and the company has enough orders to keep the factory production at 10,000 helmets per month (80% of its full capacity). Ohno’s monthly manufacturing cost and other expense data are as follows. Rent on factory equipment $11,700 Insurance on factory building 2,120 Raw materials (plastics, polystyrene, etc.) 80,100 Utility costs for factory 980 Supplies for general office 410 Wages for...
Paul Stanley specializes in manufacturing motorcycle helmets. During the current period, the following costs were incurred....
Paul Stanley specializes in manufacturing motorcycle helmets. During the current period, the following costs were incurred. For each cost, indicate whether the cost would be considered to be DM--direct material; DL--direct labor; OH--factory overhead; or PC-period cost. 1. Maintenance costs on factory building _______ 2. Factory manager's salary ________ 3. Advertising for helmets ________ 4. Sales commissions ________ 5. Depreciation on factory building ________ 6. Rent on factory equipment ________ 7. Insurance on factory building ________ 8. Plastic used to...
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding...
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding 3 years, Bell had been a retailer of audio systems. After a thorough survey of audio system markets, Bell decided to turn its retail store into an audio equipment factory. Raw materials cost for an audio system will total $74 per unit. Workers on the production lines are on average paid $12 per hour. An audio system usually takes 5 hours to complete. In...
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding...
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding 3 years, Bell had been a retailer of audio systems. After a thorough survey of audio system markets, Bell decided to turn its retail store into an audio equipment factory. Raw materials cost for an audio system will total $ 75 per unit. Workers on the production lines are on average paid $ 13 per hour. An audio system usually takes  7 hours to complete....
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding...
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding 3 years, Bell had been a retailer of audio systems. After a thorough survey of audio system markets, Bell decided to turn its retail store into an audio equipment factory. Raw materials cost for an audio system will total $77 per unit. Workers on the production lines are on average paid $14 per hour. An audio system usually takes 5 hours to complete. In...
Problem 14-2A (Part Level Submission) Bell Company, a manufacturer of audio systems, started its production in...
Problem 14-2A (Part Level Submission) Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding 3 years, Bell had been a retailer of audio systems. After a thorough survey of audio system markets, Bell decided to turn its retail store into an audio equipment factory. Raw materials cost for an audio system will total $74 per unit. Workers on the production lines are on average paid $12 per hour. An audio system usually takes...