Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $195,940. Estimated direct labor cost was $465,600 for 19,400 hours.

Actual costs for the most recent month are summarized here:

Item Description Total Cost
Direct labor (1,940 hours) $ 46,561
Indirect costs
Indirect labor 2,530
Indirect materials 3,360
Factory rent 3,230
Factory supervision 4,820
Factory depreciation 5,650
Factory janitorial work 1,210
Factory insurance 1,790
General and administrative salaries 4,140
Selling expenses 5,480


Required:
1.
Calculate the predetermined overhead rate.

2. Calculate the amount of applied manufacturing overhead.

3. Calculate actual manufacturing overhead costs.

4. Compute over- or underapplied overhead.

Homework Answers

Answer #2

1. Predetermined overhead rate = Estimated manufacturing overhead/ Estimated no of hours

=$195,940/19,400

=$10.1

2. Applied manufacturing overhead = 1,940×$10.1 =$19,594

3. Actual manufacturing overhead

Indirect labor $2,530
Indirect materials $3,360
Factory rent $3,230
Factory supervision $4,820
Factory Depreciation $5,650
Factory janitorial work $1,210
Factory insurance $1,790
Actual manufacturing overhead $22,590

4.

Actual manufacturing overhead =$22,590

Applied overhead =$19,594

Overhead Underapplied =$2,996($22,590-$19,594)

answered by: anonymous
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $172,960. Estimated direct labor cost was $454,480 for 18,400 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,840 hours) $ 45,449 Indirect costs Indirect labor 2,510 Indirect materials 3,440 Factory rent 3,280 Factory supervision 4,770 Factory...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $179,540. Estimated direct labor cost was $456,490 for 19,100 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,910 hours) $ 45,650 Indirect costs Indirect labor 2,420 Indirect materials 3,430 Factory rent 3,370 Factory supervision 4,860 Factory...
E2-18 (Algo) Calculating Actual and Applied Manufacturing Overhead Costs and Over- or Underapplied Overhead Costs [LO...
E2-18 (Algo) Calculating Actual and Applied Manufacturing Overhead Costs and Over- or Underapplied Overhead Costs [LO 2-3, 2-4, 2-5, 2-6] Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $193,000. Estimated direct labor cost was $478,640 for 19,300 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct...
Chloe Corp uses a job order costing system with manufacturing overhead applied to products on the...
Chloe Corp uses a job order costing system with manufacturing overhead applied to products on the basis of direct labor hours. For the upcoming year, Chloe Corp estimated total manufacturing overhead cost at $784,700 and total direct labor hours of 41,300. During the year actual manufacturing overhead incurred was $749,000 and 40,900 direct labor hours were used. (a) Calculate the predetermined overhead rate. (b) Calculate how much manufacturing overhead will be applied to production. (c) Is overhead over - or...
Baxter Corp uses a normal job order costing system with manufacturing overhead applied to products on...
Baxter Corp uses a normal job order costing system with manufacturing overhead applied to products on the basis of direct labor hours. For the upcoming year, Baxter Corp estimated total manufacturing overhead cost at $480,000 and total direct labor hours of 40,000. During the year actual manufacturing overhead incurred was $462,500 and 41,000 direct labor hours were used. a. Calculate the predetermined overhead rate. b. Calculate how much manufacturing overhead will be applied to production. c. Is overhead over- or...
At Becky's biscuit factory, manufacturing overhead is applied based on direct labor cost. At the beginning...
At Becky's biscuit factory, manufacturing overhead is applied based on direct labor cost. At the beginning of 2018, Becky's cost accountant estimated the following information for the year: Total DM Costs: $800,000 Direct Labor Hours: 63,000 hours Cost per DLH: $15/hour Total Machine Hours: 3,150 Total MOH Costs: $692,000 At the end of 2018, the cost accountant noted that actual direct labor hours were 56,000, actual machine hours were 3,520, and the actual labor rate was $18.48. How much manufacturing...
Callen Corp uses a normal job order costing system with manufacturing overhead applied to products on...
Callen Corp uses a normal job order costing system with manufacturing overhead applied to products on the basis of machine hours. For the upcoming year, Callen Corp estimated total manufacturing overhead cost at $270,000 and total machine hours of 45,000. During the year, actual manufacturing overhead incurred was $258,750 and 46,600 machine hours were used. a. Calculate the predetermined overhead rate. b. Calculate how much manufacturing overhead will be applied to production. c. Is overhead over- or underapplied? By how...
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct...
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 93,000 and estimated factory overhead is $511,500. The following information is for September of the current year. Job A was completed during September, and Job B was started but not finished September 1, inventories        Materials inventory $ 8,400    Work-in-process inventory (All Job A) 33,000    Finished goods...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,240,200 in manufacturing overhead cost at an activity level of 573,000 machine-hours. The company spent the entire month of January working on a large order for 8,400 custom made machined parts. The company had no...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,170,000 in manufacturing overhead cost at an activity level of 556,000 machine-hours. The company spent the entire month of January working on a large order for 8,900 custom made machined parts. The company had no...