Question

Assume that $102,000 is budgeted for fixed overhead. $95,000 was actually spent on fixed overhead. Fixed...

Assume that $102,000 is budgeted for fixed overhead. $95,000 was actually spent on fixed overhead. Fixed overhead is applied to production at $10 per labor hour, and the achieved output was 5,000 units. The standard labor hours are 2 hours per unit.

The total fixed overhead variance is $2,000 favorable.

All of these choices are correct.

The fixed overhead spending variance is $7,000 favorable.

The fixed overhead volume variance is $5,000 unfavorable.

Homework Answers

Answer #1

Solution:

Budgeted fixed overhead = $102,000

Actual fixed overhead = $95,000

Fixed overhead applied = SH * SR = 5000*2*$10 = $100,000

Total fixed overhead variance = Fixed overhead applied - actual fixed overhead = $100,000 - $95,000 = $5,000 F

Fixed overhead spending variance = Budgeted fixed overhead - Actual fixed overhead = $102,000 - $95,000 = $7,000 Favorable

Fixed overhead volume variance = Fixed overhead applied - Budgeted fixed overhead = $100,000 - $102,000 = $2,000 unfavorable

Hence 3rd option is correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following information relating to a company's overhead costs is available. Budgeted fixed overhead rate per...
The following information relating to a company's overhead costs is available. Budgeted fixed overhead rate per machine hour $ 0.50 Actual variable overhead $ 73,000 Budgeted variable overhead rate per machine hour $ 2.50 Actual fixed overhead $ 17,000 Budgeted hours allowed for actual output achieved 32,000 Based on this information, the total overhead variance is: Multiple Choice $6,000 favorable. $1,000 favorable. $7,000 favorable. $6,000 unfavorable. $1,000 unfavorable.
The following information applies to questions 1-3: Actual fixed overhead cost: $35,200 Budgeted fixed overhead cost:...
The following information applies to questions 1-3: Actual fixed overhead cost: $35,200 Budgeted fixed overhead cost: $35,000 Budgeted fixed overhead rate, based on 10,000 machine hours: $3.50 Standard machine hours per unit: 1/2 hour Actual units produced: 17,600 1.          Compute the fixed overhead budget variance: a. $4,400 favorable              c. $4,200 favorable b. $200 unfavorable              d. $200 favorable 2.          Compute the fixed overhead volume variance: a. $200 unfavorable             c. $200 favorable b. $4,400 favorable               d. $4,200 unfavorable...
Question 22 options: Everjoice Company makes clocks. The budgeted fixed overhead costs for 2012 totaled $720,000....
Question 22 options: Everjoice Company makes clocks. The budgeted fixed overhead costs for 2012 totaled $720,000. The company uses direct labor hours to allocated fixed overhead and it takes 0.5 direct labor hours per clock. The budgeted quantity of clocks (output) planned for the year was 480,000 units. During the year, 504,000 clocks were produced and $780,000 was spent on fixed overhead. A. What is the fixed overhead rate (FOH rate) for 2012 based on direct labor hours? B. The...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 6,800 units of product were as follows: Standard Costs Actual Costs Direct materials 8,800 lb. at $4.90 8,700...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead costs are applied to products on the basis of machine hours. The denominator volume of machine hours is 9,000. Standard Quantity or Hours per unit Standard Price or Rate per unit Standard Cost per unit Direct Materials 3 feet $6 per foot $18 Direct Labor 1.5 direct labor hours $10 per direct labor hour $15 Variable Overhead 2 machine hours $12 per machine hour...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $98,500 Fixed factory overhead 38,500 Standard: 7,000 hrs. at $18 126,000 If productive capacity of 100% was 11,000 hours and the factory overhead cost budgeted at the level of 7,000 standard hours was $140,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $297,100 Fixed factory overhead 68,750 Standard: 7,000 hrs. at $50 350,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $375,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead...
Answer questions 18-21 using the information below: Thinnews Co., uses machine hours to allocate manufacturing overhead cost to outputs: Actual total overhead cost incurred $ 24,000 Actual fixed overhead cost incurred $ 10,000 Budgeted fixed overhead cost $ 11,000 Actual machine hours 5,000 Standard machine hours allowed for the units manufactured 4,800 Denominator level — machine hours 5,500 Standard variable overhead rate per machine hour $ 3.00 What is variable overhead spending variance? Group of answer choices $960 favorable $1,000...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead...
Lee Company's standards for the most recent period are given below. Fixed and variable manufacturing overhead costs are applied to products on the basis of machine hours. The denominator volume of machine hours is 9,000. Standard Quantity or Hours per unit Standard Price or Rate per unit Standard Cost per unit Direct Materials 3 feet $6 per foot $18 Direct Labor 1.5 direct labor hours $10 per direct labor hour $15 Variable Overhead 2 machine hours $12 per machine hour...
Lihue, Inc., applies fixed overhead at the rate of $4.20 per unit. Budgeted fixed overhead was...
Lihue, Inc., applies fixed overhead at the rate of $4.20 per unit. Budgeted fixed overhead was $1,457,820. This month 342,100 units were produced, and actual overhead was $1,450,000. Required A What are the fixed overhead price and production volume variances for Lihue? (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.) Fixed overhead price variance    Fixed overhead production volume variance Required B: What...