Question

43. Reyes Corporation applies overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead...

43. Reyes Corporation applies overhead using a normal costing approach based upon machine-hours. Budgeted factory overhead was $273,020, budgeted machine-hours were 18,700. Actual factory overhead was $289,920, actual machine-hours were 19,250. How much overhead would be applied to production?

$281,637.

$289,920.

$273,020.

$281,050.

44. Dockside Enterprises, Inc., operates two divisions: (1) a management division that owns and manages bulk carriers on the Great Lakes and (2) a repair division that operates a dry dock in Tampa, Florida. The repair division works on company ships, as well as other large-hull ships. The repair division has an estimated variable cost of $31 per labor-hour. The repair division has a backlog of work for outside ships. They charge $71 per hour for labor, which is standard for this type of work. The management division complained that it could hire its own repair workers for $41 per hour, including leasing an adequate work area.

What is the maximum transfer price per hour that the management division should pay?

$31.

$40.

$71.

$41.

45. The following information summarizes the standard cost for producing one metal tennis racket frame at Spaulding Industries. In addition, the variances for one month's production are given. Assume that all inventory accounts have zero balances at the beginning of the month.

Standard Cost Per Unit Standard Monthly Costs
Materials $ 4.00 $ 8,500
Direct Labor 3 hrs. @ $2.50 7.50 15,000
Factory Overhead:
Variable 1.60 3,200
Fixed 5.10 10,200
$ 18.20 $ 36,900
Variances:
Material price 337.50 unfavorable
Material quantity 500.00 unfavorable
Labor rate 550.00 favorable
Labor efficiency 2,150.00 unfavorable

What was the actual price paid for the direct material during the month, assuming all materials purchased were put into production?

$4.39.

$4.15.

$4.00.

$4.22.

Homework Answers

Answer #1

Solution 43:

Predetermined overhead rate = Budgeted overhead / Budgeted machine hours = $273,020 / 18700 = $14.60 per machine hour

Overhead applied = Actual machine hours * Overhead rate = 19250*$14.60 = $281,050

Hence last option is correct.

Solution 44:

Maximum transfer price that management division should pay is hiring cost of own repair workers = $41 per hour

Hence last option is correct.

Solution 45:

Actual cost of material = Standard cost + Unfavorable material price variance + Unfavorable material quantity variance

= $8,500 + $337.50 + $500 = $9,337.50

Standard Quantity of material = $8,500 / $4 = 2125 units

Material quantity variance = $500 U

(SQ - AQ) * SP = -$500

(2125 - AQ) * $4 = - $500

Actual quantity purchased and used = 2250 units

Actual price paid for direct material = $9,337.50 / 2250 = $4.15 per unit

Hence 2nd option is correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ackson Inc. listed the following data for 2016: Budgeted factory overhead $1,271,000 Budgeted direct labor hours...
ackson Inc. listed the following data for 2016: Budgeted factory overhead $1,271,000 Budgeted direct labor hours 82,000 Budgeted machine hours 41,000 Actual factory overhead 1,201,000 Actual direct labor hours 86,300 Actual machine hours 39,400 Round calculations to 2 significant digits If overhead is applied based on direct labor hours, overapplied/underapplied overhead is: $136,650 overapplied. $136,650 underapplied. $174,775 underapplied. $174,775 overapplied. $-0-. Sutherland Company listed the following data for 2016: Budgeted factory overhead $2,100,000 Budgeted direct labor hours 89,000 Budgeted machine...
Budgeted factory overhead of SOLANO Corp. was $399,600 and the budgeted machine-hours were 27,750. Actual factory...
Budgeted factory overhead of SOLANO Corp. was $399,600 and the budgeted machine-hours were 27,750. Actual factory overhead was $431,880 and actual machine-hours were 28,575. Solano Corporation applies overhead based upon machine-hours. Before disposition of under/overapplied overhead, the cost of goods sold was $840,000 and ending inventories were as follows: Direct materials $ 90,000 WIP 285,000 Finished goods 375,000 Total $750,000 Required: a. Determine the budgeted factory overhead rate per machine-hour. b. Compute the over/underapplied overhead. c. Prepare the journal entry...
Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual...
Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below: Original Budget Actual Costs Variable overhead costs: Supplies $ 6,400 $ 6,590 Indirect labor 10,580 9,930 Fixed overhead costs: Supervision 14,210 14,350 Utilities 13,500 13,550 Factory depreciation 57,440 57,250 Total overhead cost $ 102,130 $ 101,670 The company based its original budget on 6,500 machine-hours. The company actually worked 6,460 machine-hours during the month. The...
Acuff Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual...
Acuff Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below: Original Budget Actual Costs Fixed overhead costs: Supervision $ 15,600 $ 15,950 Utilities 5,000 5,070 Factory depreciation 6,800 6,700 Total overhead cost $ 27,400 $ 27,720 The company based its original budget on 6,200 machine-hours. The company actually worked 6,560 machine-hours during the month. The standard hours allowed for the actual output of the month...
Rodarta Corporation applies manufacturing overhead to products on the basis of standard machine-hours. The company's predetermined...
Rodarta Corporation applies manufacturing overhead to products on the basis of standard machine-hours. The company's predetermined overhead rate for fixed manufacturing overhead is $4.10 per machine-hour and the denominator level of activity is 4,300 machine-hours. In the most recent month, the total actual fixed manufacturing overhead was $17,730 and the company actually worked 4,230 machine-hours during the month. The standard hours allowed for the actual output of the month totaled 4,250 machine-hours. What was the overall fixed manufacturing overhead volume...
Sutherland Company listed the following data for 2019: Budgeted factory overhead $2,223,000 Budgeted direct labor hours...
Sutherland Company listed the following data for 2019: Budgeted factory overhead $2,223,000 Budgeted direct labor hours 90,000 Budgeted machine hours 50,000 Actual factory overhead 2,201,800 Actual direct labor hours 84,500 Actual machine hours 45,400 If overhead is applied based on machine hours, the overapplied/underapplied overhead is (round calculations to 2 significant digits):
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $676,900 $676,500 Estimated direct labor hours for year 12,300 Estimated machine hours for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $498,200 $768,000 Estimated direct labor hours for year 12,000 Estimated machine hours for year 24,910 Actual factory overhead costs for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $685,980 $672,000 Estimated direct labor hours for year 10,500 Estimated machine hours for year 18,540 Actual factory overhead costs for...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $98,500 Fixed factory overhead 38,500 Standard: 7,000 hrs. at $18 126,000 If productive capacity of 100% was 11,000 hours and the factory overhead cost budgeted at the level of 7,000 standard hours was $140,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT