Question

1- The fixed costs per unit are OMR 9.6 when a company produces 10,000 units of...

1-

The fixed costs per unit are OMR 9.6 when a company produces 10,000 units of product. What are the fixed costs per unit when 8,000 units are produced?

Select one:

a.
11.2

b.

12

c.

9.6

d.
8

2-

The following data pertain to the current period:

Budgeted machine hours for the current period             80,000 hrs.

Budgeted manufacturing overhead                                  OMR 980,000

Actual machine hours                                                       90,000. Hrs.

Actual manufacturing overhead                           OMR 800,000.

On the basis of this information, the company's year-end overhead was:

Select one:

a.
Over-applied by 302,500.

b.
Over-applied by 80,000.

c.
Under-applied by 80,000.

d.
Under-applied by 302,500.

Homework Answers

Answer #1
1 Total Fixed Costs incurred(10000*OMR 9.6) OMR 96,000
Fixed Cost per unit at 8000 units(OMR 96,000 / 8000) OMR 12
So Option C is answer
2 Budgeted Overhead Rate =Budgeted manufacturing overhead / Budgeted machine hours
Budgeted Overhead Rate =OMR 980,000 / 80,000 hours =$12.25 per machine hours
Manufacturing overhead applied =Budgeted Overhead Rate*Actual direct machine hours
Manufacturing overhead applied =OMR12.25*90,000 hours =OMR 1,102,500
Actual Manufacturing overhead =OMR 800,000
Overapplied Manufacturing Overhead = Manufacturing overhead applied - Actual Manufacturing overhead
Overapplied Manufacturing Overhead =OMR 1,102,500 - OMR 800,000 =OMR 302,500
So Option A is answer
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1- Denver Enterprises recently used 14,000 labor hours to produce 7,500 completed units. According to manufacturing...
1- Denver Enterprises recently used 14,000 labor hours to produce 7,500 completed units. According to manufacturing specifications, each unit is anticipated to take two hours to complete. The company's actual payroll cost amounted to OMR 158,200. If the standard labor cost per hour is OMR 11, Denver's labor efficiency variance is: Select one: a. 11,000 F b. 11,300 UNF c. 11,000 UNF d. 11,300 F 2- The following data pertain to the current year: Budgeted manufacturing overhead:                     OMR 450,000...
PROBLEM: 1 (MUST SHOW CALCULATIONS; NO CALCULATIONS NO CREDIT) BUDGETED DATA: Budgeted machine hours                         &nbs
PROBLEM: 1 (MUST SHOW CALCULATIONS; NO CALCULATIONS NO CREDIT) BUDGETED DATA: Budgeted machine hours                                                              60,000 machine hours Budgeted direct labor hours                                                        400,000 direct labor hours Budgeted direct labor costs                                                         $6,000,000 Budgeted manufacturing overhead costs                              $10,000,000 Company allocates manufacturing overhead using direct labor hours used ACTUAL DATA: Actual manufacturing overhead costs incurred                    $9,700,000 Actual machine hours used                                                          62,000 machine hrs used Actual direct labor hours used                                                    380,000 actual DL hours used Calculate budgeted (applied) manufacturing overhead rate per direct labor hour...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
1) Determining Budgeted Overhead The overhead application rate for a company is $12 per unit, made...
1) Determining Budgeted Overhead The overhead application rate for a company is $12 per unit, made up of $7 per unit of fixed overhead and $5 per unit of variable over- head. Normal capacity is 10,000 units. In one month, there was a favorable flexible budget variance of $2,500. Actual overhead for the month was $110,000 and actual units produced were 15,125. Based on this information, determine the amount of the budgeted overhead for the actual level of production. 2)...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4 per Ib.) $ 120.00 Direct labor (5 hrs. @ $14 per hr.) 70.00 Factory overhead—Variable (5 hrs. @ $8 per hr.) 40.00 Factory overhead—Fixed (5 hrs. @ $10 per hr.) 50.00 Total standard cost $ 280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the most recent month: Machine-hour standard: Two machine hours per unit Standard fixed overhead rate: $20 per machine hour Actual production: 15,000 units Under-applied fixed overhead: $50,000 Fixed overhead budget variance: $30,000 favorable The budgeted fixed overhead and the fixed overhead volume variance, respectively, are $620,000 and $20,000 $680,000 and -$80,000 $650,000 and $50,000...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT