Question

Efficient Corporation uses a standard cost system. The following information was provided for the period that...

Efficient Corporation uses a standard cost system. The following information was provided for the period that just ended:

Actual price per gallon $11.75
Actual gallons of material used 5,000
Actual hourly labor rate $17.00
Actual hours of production 24,300
Standard price per gallon $12.00
Standard gallons per completed unit 1/2
Standard hourly labor rate $12.00
Standard time per completed unit 3 hrs.
Units completed during the period 9,000

Refer to the information provided for Efficient Corporation. The direct materials cost variance is:

a.

$1,125 favorable.

b.

$4,750 unfavorable.

c.

$6,000 unfavorable.

d.

$7,125 unfavorable.

Homework Answers

Answer #1

Material cost variance is the difference between the standard cost of materials and actual cost of materials. If the actual cost is more than the standard cost then the variance is unfavourable and if the actual cost is less than the standard cost then the variance is favourble.

Standard material for 9,000 units = 9,000*1/2 = 4,500 gallons

Standard material cost = 4,500*12 = $54,000

Actual material cost = 5,000*11.75 = $58,750

Material cost variance = 54,000-58,750 = $4,750 unfavourable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use this information for Stringer Company to answer the question that follow. The following data are...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,949     Actual price paid for materials $22,445 Labor:     Standard hourly labor rate $14.96 per hour     Standard hours allowed per completed unit 4.6     Actual labor hours worked 5,474.45     Actual total labor costs $83,485 Overhead:...
A company provided the following direct materials cost information. Compute the direct materials quantity variance. Standard...
A company provided the following direct materials cost information. Compute the direct materials quantity variance. Standard costs assigned: Direct materials standard cost (492,000 units @ $2.70/unit) $ 1,328,400 Actual costs: Direct materials costs incurred (490,070 units @ $3.00/unit) $ 1,470,210 Multiple Choice $141,810 Favorable. $5,790 Unfavorable $5,790 Favorable. $5,211 Favorable. $5,211 Unfavorable. Hassock Corp. produces woven wall hangings. It takes 4 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $12 per hour. During...
Budgeted production 26,000 units Actual production 27,500 units Labor:   Standard hourly labor rate $22 per hour...
Budgeted production 26,000 units Actual production 27,500 units Labor:   Standard hourly labor rate $22 per hour   Standard hours allowed per completed unit 6.6   Actual labor hours worked 183,000   Actual total labor costs $4,020,000 What is the labor price variance? 5,490 unfavorable 5,490 favorable 33,000 favorable 33,000 unfavorable
Neptune Inc. uses a standard cost system and has the following information for the most recent...
Neptune Inc. uses a standard cost system and has the following information for the most recent month, April: Actual direct labor hours (DLHs) worked 17,000 Standard direct labor hours allowed for good output produced this period 18,000 Actual total factory overhead costs incurred $45,400 Budgeted fixed factory overhead costs $10,800 Denominator activity level, in direct labor hours (DLHs) 15,000 Total factory overhead application rate per standard direct labor hour $2.70 The variable factory overhead efficiency variance for Neptune, Inc. in...
Use the following information for the Exercises below. [The following information applies to the questions displayed...
Use the following information for the Exercises below. [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials (7 lbs. @ $7 per lb.) 62,900 lbs. @ $7.10 per lb. Direct labor (3 hrs. @ $16 per hr.) 26,500 hrs. @ $16.50 per hr. Overhead (3 hrs. @ $13 per hr.) $ 352,600 Units manufactured 8,900 Exercise 23-8 Standard unit cost; total cost variance LO C2 (1) Compute...
Amos,Inc. uses a standard cost system in which direct material is carried at standard cost. Standards...
Amos,Inc. uses a standard cost system in which direct material is carried at standard cost. Standards for One unit includes a standard quantity of 8.5 gallons and a standard price $1.85 per Gallon. During March, Amos Purchased 150000 Gallons of direct material at cost of 300000 and used 150500 gallons in production of 18000 units (there was adequated beginning inventory to allow for the extra material that was used). Calcualate the direct material price and quantity variances and circle whether...
Neptune Inc. uses a standard cost system and has the following information for the most recent...
Neptune Inc. uses a standard cost system and has the following information for the most recent month, April: Actual direct labor hours (DLHs) worked 13,000 Standard DLHs allowed for good output produced this period 19,000 Actual total factory overhead costs incurred $ 38,000 Budgeted fixed factory overhead costs $ 10,600 Denominator activity level, in direct labor hours (DLHs) 15,000 Total factory overhead application rate per standard DLH $ 2.70 The total factory overhead flexible-budget variance in April for Neptune, Inc.,...
Shade Company adopted a standard cost system several years ago. The standard costs for direct labor...
Shade Company adopted a standard cost system several years ago. The standard costs for direct labor and direct materials for its single product are as follows: Materials (5 kilograms × $12.00/kilogram) = $60.00/unit. Direct labor (3.5 hours/unit × $20.00/hour) = $70.00/unit. All materials were issued at the beginning of processing. The operating data shown below were taken from the records for December: In-process beginning inventory None In-process ending inventory—80% complete as to labor 960 units Units completed during the period...
     The accountant of JYD Corporation prepared the following cost analysis report on direct labor costs...
     The accountant of JYD Corporation prepared the following cost analysis report on direct labor costs for the jobs completed during the previous months: Job         Actual Hrs. at Actual Rates           Actual Hrs. at Standard Rates      Standard Hrs. at Standard Rates 105         P2,270                                                   P2,590                                                   P2,170 110         10,740                                                   10,970                                                   10,500 117         4,730                                                   4,900                                                   4,620 120         13,850                                                   13,600                                                   13,480 Total      P31,590                                P32,060                                P30,770 What is the total direct labor variance for the jobs completed? What is the labor rate variance? What is...
Barley Hopp, Inc., manufactures custom-ordered commemorative beer steins. Its standard cost information follows: Standard Quantity Standard...
Barley Hopp, Inc., manufactures custom-ordered commemorative beer steins. Its standard cost information follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (clay) 1.70 lbs. $ 1.80 per lb. $ 3.06 Direct labor 1.70 hrs. $ 10.00 per hr. 17.00 Variable manufacturing overhead (based on direct labor hours) 1.70 hrs. $ 1.10 per hr. 1.87 Fixed manufacturing overhead ($402,500.00 ÷ 175,000.00 units) 2.30 Barley Hopp had the following actual results last year: Number of units produced and sold 180,000...